Market Notices

119334MARKET INTERVENTION24/10/2024 04:02:52 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119237

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 25/10/2024.

The direction update is issued at 1600 hrs 24/10/2024.

Manager NEM Real Time Operations
119310MARKET INTERVENTION24/10/2024 06:30:06 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 119265

Direction is cancelled from: 1830 hrs 24/10/2024

Manager NEM Real Time Operations
119309MARKET INTERVENTION24/10/2024 03:36:54 PM

Cancellation - AEMO Intervention Event - VIC region 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - VIC region 24/10/2024

Refer to Market Notice 119272

The AEMO Intervention Event and all associated directions are cancelled from 1535 hrs on 24/10/2024.


Manager NEM Real Time Operations
119308MARKET INTERVENTION24/10/2024 03:34:14 PM

Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-3 MURRAY2

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-3 MURRAY2

Refer to Market Notice 119293

Direction is cancelled from: 1535 hrs 24/10/2024

Manager NEM Real Time Operations
119307MARKET INTERVENTION24/10/2024 03:33:02 PM

Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2

Refer to Market Notice 119292

Direction is cancelled from: 1535 hrs 24/10/2024

Manager NEM Real Time Operations
119306RESERVE NOTICE24/10/2024 01:42:15 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1800 hrs to 1900 hrs 28/10/2024.
The forecast capacity reserve requirement is 607 MW.
The minimum capacity reserve available is 517 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations

119293MARKET INTERVENTION24/10/2024 12:19:56 PM

Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2

Refer AEMO Electricity Participant Notice 119271

The MURR2-3 MURRAY2 direction is now expected to stay in place until 1700 hrs 24/10/2024.

The direction update is issued at 1215 hrs 24/10/2024.

Manager NEM Real Time Operations
119292MARKET INTERVENTION24/10/2024 12:18:10 PM

Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2

Refer AEMO Electricity Participant Notice 119270

The MURR2-2 MURRAY2 direction is now expected to stay in place until 1700 hrs 24/10/2024.

The direction update is issued at 1215 hrs 24/10/2024.

Manager NEM Real Time Operations
119272MARKET INTERVENTION24/10/2024 08:01:14 AM

Direction - VIC region 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - VIC region 24/10/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the VIC region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 0800 hrs on 24/10/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations