Filter by category
Filter by Date
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119199
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/10/2024.
The direction update is issued at 1600 hrs 23/10/2024.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack of Reserve Level 1 (LOR1) in the NSW Region on 25/10/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119162 is cancelled at 1400 hrs 23/10/2024.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 24/10/2024 to 1930 hrs 24/10/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 774 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 24/10/2024 to 1930 hrs 24/10/2024.
The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 1306 MW.
Manager NEM Real Time Operations
CHG0099235 | Production | Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Change Number: CHG0099235
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Change Start Date & Time: 24/10/2024 10:00:00 AEST
Change End Date & Time: 24/10/2024 16:00:00 AEST
Outage Start Date & Time: 24/10/2024 11:57:00 AEST
Outage End Date & Time: 24/10/2024 12:02:00 AEST
Environment: Production
Participant Impact and Requirements:
Planned maintenance has been scheduled for the 24th October, commencing 11:57am - 12:02pm AEST. During this time there will be a brief outage (Up to 30 seconds) impacting the following Pre-Production systems:
- MSATS Retail
- EMMS Wholesale
- GAS Market Systems
- WA Market Systems
The maintenance being carried out relates to infrastructure only, no application or functional changes are being performed. If you experience system related issues beyond the outage window (12:02pm) please contact the AEMO Support Hub.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0099241 | Production | Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Change Start Date & Time: 24/10/2024 10:00:00 AEST
Change End Date & Time: 24/10/2024 16:00:00 AEST
Outage Start Date & Time: 24/10/2024 11:57:00 AEST
Outage End Date & Time: 24/10/2024 12:02:00 AEST
Environment: Production
Participant Impact and Requirements:
Planned maintenance has been scheduled for the 24th October, commencing 11:57am - 12:02pm AEST. During this time there will be a brief outage (Up to 30 seconds) impacting the following Pre-Production systems:
- MSATS Retail
- EMMS Wholesale
- GAS Market Systems
- WA Market Systems
The maintenance being carried out relates to infrastructure only, no application or functional changes are being performed. If you experience system related issues beyond the outage window (12:02pm) please contact the AEMO Support Hub.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119200
The updated required actions: Synchronise and follow dispatch targets at 0845 hrs 23/10/2024
The direction update is issued at 0830 hrs 23/10/2024.
Manager NEM Real Time Operations
Direction - SA region 22/10/2024 to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region 22/10/2024 to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 119195
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1630 hrs 22/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0830 hrs 23/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 24/10/2024.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 22/10/2024 to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Direction - SA region 22/10/2024 to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 119195
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1630 hrs 22/10/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0800 hrs 23/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 24/10/2024.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations