122982NON-CONFORMANCE09/01/2025 08:30:19 AM

NON-CONFORMANCE Region QLD1 Thursday, 9 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 9 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KINGASF1
Duration: 09/01/2025 08:15 to 09/01/2025 08:30
Amount: 35 MW
Constraint: NC-Q_KINGASF1

Auto-generated on behalf of Manager NEM Real Time Operations
122962INTER-REGIONAL TRANSFER08/01/2025 12:20:09 PM

Inter-regional transfer limit variation - Hummocks - Bungama - Snowtown 132kV Line - SA region - 08/01/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama - Snowtown 132kV Line - SA region - 08/01/2025

At 1210 hrs 08/01/2025 there was a short notice outage of Hummocks - Bungama - Snowtown 132kV Line.

The following constraint set(s) invoked at 1210 hrs 08/01/2025
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
122961INTER-REGIONAL TRANSFER08/01/2025 12:09:21 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 08/01/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_56906542 from 1155 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1
VIC1-NSW1

Manager NEM Real Time Operations
122920INTER-REGIONAL TRANSFER07/01/2025 03:36:39 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 07/01/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_BRIS_5687999A from 0330 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
122824NON-CONFORMANCE03/01/2025 10:15:14 PM

NON-CONFORMANCE Region QLD1 Friday, 3 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 3 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 03/01/2025 21:35 to 03/01/2025 22:15
Amount: -57 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
122647NON-CONFORMANCE01/01/2025 12:45:12 AM

NON-CONFORMANCE Region QLD1 Wednesday, 1 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 1 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 01/01/2025 00:00 to 01/01/2025 00:45
Amount: 40 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations