Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127413
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 07/06/2025.
The direction update is issued at 0915 hrs 07/06/2025.
Manager NEM Real Time Operations
[EventId:202506061740_confirmed] Prices for interval 06-Jun-2025 17:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:40.
In accordance with Market Notice 127420 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506061800_confirmed] Prices for interval 06-Jun-2025 18:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 18:00.
In accordance with Market Notice 127425 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506061755_confirmed] Prices for interval 06-Jun-2025 17:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:55.
In accordance with Market Notice 127424 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506061750_confirmed] Prices for interval 06-Jun-2025 17:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:50.
In accordance with Market Notice 127423 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506061745_confirmed] Prices for interval 06-Jun-2025 17:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:45.
In accordance with Market Notice 127422 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506061735_confirmed] Prices for interval 06-Jun-2025 17:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:35.
In accordance with Market Notice 127417 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 06/06/2025 to 1800 hrs 06/06/2025.
The forecast capacity reserve requirement is 1598 MW.
The minimum capacity reserve available is 1551 MW.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127412
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1630 hrs 06/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 1900 hrs 06/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/06/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations