127657MARKET SYSTEMS18/06/2025 10:50:12 AM

Initial - CHG0104258 - Telco Outage Notification - Telstra Perth PSTN Indial (08 9469 95XX-99XX)

Change Number: CHG0104258

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Perth PSTN Indial (08 9469 95XX-99XX)
Change Start Date & Time: 18/06/2025 02:00:00
Change End Date & Time: 18/06/2025 08:00:00
Outage Start Date & Time: 18/06/2025 02:00:00
Outage End Date & Time: 18/06/2025 06:00:00
Environment: Production
Participant Impact and Requirements: Outage Duration:
1 x 10-minutes outage within the outage window

Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Melbourne).

Action Required:
If a call is in progress and subsequently dropped by the outage, the caller will need to initiate the phone call again.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
     
127656MARKET SYSTEMS18/06/2025 10:47:21 AM

Initial - CHG0103463 - EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0103463

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 19/06/2025 08:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:00
Outage End Date & Time: 19/06/2025 19:00:00
Environment: Production
Participant Impact and Requirements: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities. During the window, delivery of FPP calculations through the participant data model may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127625MARKET SYSTEMS17/06/2025 10:38:08 AM

Initial - CHG0103463 - EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities

Change Number: CHG0103463

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 19/06/2025 08:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:00
Outage End Date & Time: 19/06/2025 19:00:00
Environment: Production
Participant Impact and Requirements: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities. During the window, delivery of FPP calculations through the participant data model may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127624MARKET SYSTEMS17/06/2025 10:32:34 AM

Completed - CHG0103273 - Scheduled Maintenance on Brisbane Datacentre

Change Number: CHG0103273

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Scheduled Maintenance on Brisbane Datacentre

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
127595NON-CONFORMANCE16/06/2025 11:30:26 AM

NON-CONFORMANCE Region VIC1 Monday, 16 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 16 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOKOSF1
Duration: 16/06/2025 11:20 to 16/06/2025 11:30
Amount: 30 MW
Constraint: NC-V_MOKOSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127584NON-CONFORMANCE16/06/2025 10:45:13 AM

NON-CONFORMANCE Region VIC1 Monday, 16 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 16 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOKOSF1
Duration: 16/06/2025 10:15 to 16/06/2025 10:45
Amount: 12 MW
Constraint: NC-V_MOKOSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127538NON-CONFORMANCE14/06/2025 12:05:21 PM

NON-CONFORMANCE Region QLD1 Saturday, 14 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 14 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YARANSF1
Duration: 14/06/2025 11:10 to 14/06/2025 12:05
Amount: 67 MW
Constraint: NC-Q_YARANSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127531MARKET SYSTEMS13/06/2025 10:58:08 AM

Initial - CHG0103468 - Identity Service Site Transfer

Change Number: CHG0103468

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Identity Service (IDS)
Change Title: Identity Service Site Transfer
Change Start Date & Time: 19/06/2025 17:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:39
Outage End Date & Time: 19/06/2025 18:15:00
Environment: Production
Participant Impact and Requirements: Identity Service is used by multiple systems for user authorisation and authentication.
Identity Service is mostly used by the following systems:
*MSATS
*APIs (EMMS, GBB, MSATS)
*WEM
*Internal / Markets Portal Services
Identity Service may cause users to experience outages or few session issues for logins initated between 18:00 to 18:15 Market Time on 19/June/2025.
Internal / Market Portal Services will have an outage due to EMMS site transfer activities carried out in parallel, under a seperate change.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127530MARKET SYSTEMS13/06/2025 10:53:37 AM

Initial - CHG0103768 - Planned maintenance affecting the AEMO Market Network

Change Number: CHG0103768

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.
Change Start Date & Time: 26/06/2025 07:00:00
Change End Date & Time: 26/06/2025 18:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 26th of June 2025, between 07:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.

During the change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm