Initial - CHG0103463 - EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 19/06/2025 08:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:00
Outage End Date & Time: 19/06/2025 19:00:00
Environment: Production
Participant Impact and Requirements: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities. During the window, delivery of FPP calculations through the participant data model may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Initial - CHG0104256 - Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Change Start Date & Time: 18/06/2025 02:00:00
Change End Date & Time: 18/06/2025 08:00:00
Outage Start Date & Time: 18/06/2025 02:00:00
Outage End Date & Time: 18/06/2025 08:00:00
Environment: Production
Participant Impact and Requirements: Outage Duration:
1 x 10 Minutes during the window
Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127651 is cancelled at 1400 hrs 18/06/2025.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
HG0103386 | Production | Renewal and update of AEMO's FBS-Prod-Hub.aemo.com.au server certificate
Participants connecting to these endpoints or receiving requests from AEMO's FRC Gas Hub platforms and have authorisation mechanisms like certificate fingerprinting in place will notice a change in AEMO's server's certificate fingerprint and will need to update their systems accordingly.
The certificate relates to "FBS-Prod-Hub.aemo.com.au" certificate and relates to the following domains.
FBS-Prod-Hub.aemo.com.au
apis.prod.aemo.com.au
hub.aemo.com.au
prod.frchub.net
apis.prod.marketnet.net.au
hub.marketnet.net.au
Participants WILL need to update the profile that communicates with the above domains.
This will need to be done to avoid the inability to send messages to the relay.
The certificates can be downloaded from the link below:
https://www.digicert.com/secure/download-certificate/0zb6n7hdvs5c84j41twxz695ft63p2m
Change duration will be as below.
Start - 22/06/2025 10:00:00 AM AEST
End - 22/06/2025 14:00:00 PM AEST
NON-CONFORMANCE Region QLD1 Wednesday, 18 June 2025
NON-CONFORMANCE QLD1 Region Wednesday, 18 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 18/06/2025 14:25 to 18/06/2025 14:40
Amount: -55 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Completed - CHG0104258 - Telco Outage Notification - Telstra Perth PSTN Indial (08 9469 95XX-99XX)
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Perth PSTN Indial (08 9469 95XX-99XX)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Initial - CHG0104258 - Telco Outage Notification - Telstra Perth PSTN Indial (08 9469 95XX-99XX)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Perth PSTN Indial (08 9469 95XX-99XX)
Change Start Date & Time: 18/06/2025 02:00:00
Change End Date & Time: 18/06/2025 08:00:00
Outage Start Date & Time: 18/06/2025 02:00:00
Outage End Date & Time: 18/06/2025 06:00:00
Environment: Production
Participant Impact and Requirements: Outage Duration:
1 x 10-minutes outage within the outage window
Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Melbourne).
Action Required:
If a call is in progress and subsequently dropped by the outage, the caller will need to initiate the phone call again.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Initial - CHG0103463 - EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 19/06/2025 08:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:00
Outage End Date & Time: 19/06/2025 19:00:00
Environment: Production
Participant Impact and Requirements: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities. During the window, delivery of FPP calculations through the participant data model may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 0600 hrs to 0800 hrs 19/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1420 MW.
2. From 1630 hrs to 2300 hrs 19/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1487 MW.
AEMO Operations