STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 09/10/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128005 is cancelled at 1000hrs 08/07/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 09/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128001 has been updated at 0900 hrs 08/07/2025 to the following:
From 2230 hrs to 2330 hrs 09/07/2025.
The forecast capacity reserve requirement is 566 MW.
The minimum capacity reserve available is 573 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128002 is cancelled at 0900 hrs 08/07/2025.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127994 has been updated to the following:
[1.] From 0000 hrs 10/07/2025 to 0100 hrs 10/07/2025.
The forecast capacity reserve requirement is 629 MW.
The minimum capacity reserve available is 596 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 09/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127993 has been updated to the following:
[1.] From 2100 hrs 09/07/2025 to 2359 hrs 09/07/2025.
The forecast capacity reserve requirement is 610 MW.
The minimum capacity reserve available is 498 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127990 has been updated at 1300 hrs 07/07/2025 to the following:
From 0000 hrs to 0100 hrs 10/07/2025.
The forecast capacity reserve requirement is 688 MW.
The minimum capacity reserve available is 659 MW.
AEMO is seeking a market response.
[AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 09/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127991 has been updated at 1300 hrs 07/07/2025 to the following:
1. From 0730 hrs to 2030 hrs 09/07/2025.
The forecast capacity reserve requirement is 767 MW.
The minimum capacity reserve available is 710 MW.
2. From 2100 hrs to 2359 hrs 09/07/2025.
The forecast capacity reserve requirement is 697 MW.
The minimum capacity reserve available is 566 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Pre-Prod eMDM Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release
Change Start Date & Time: 09/07/2025 13:00:00
Change End Date & Time: 09/07/2025 17:00:00
Outage Start Date & Time: 09/07/2025 13:00:00
Outage End Date & Time: 09/07/2025 17:00:00
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 09/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127989 has been updated at 1100 hrs 07/07/2025 to the following:
From 0600 hrs to 2359 hrs 09/07/2025.
The forecast capacity reserve requirement is 729 MW.
The minimum capacity reserve available is 566 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations