127560RESERVE NOTICE15/06/2025 02:25:24 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1800 hrs 17/06/2025 to 2230 hrs 17/06/2025.
The forecast capacity reserve requirement is 644 MW.
The minimum capacity reserve available is 594 MW.


Manager NEM Real Time Operations
     
127555RESERVE NOTICE15/06/2025 01:12:11 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1700 hrs 15/06/2025 to 1830 hrs 15/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 669 MW.


Manager NEM Real Time Operations
     
127553RESERVE NOTICE15/06/2025 10:37:06 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127552 is cancelled at 1035 hrs 15/06/2025.

Manager NEM Real Time Operations
     
127552RESERVE NOTICE15/06/2025 08:25:18 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1730 hrs 15/06/2025 to 1830 hrs 15/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 723 MW.


Manager NEM Real Time Operations
     
127548RESERVE NOTICE15/06/2025 01:50:06 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127547 is cancelled at 0140 hrs 15/06/2025.

Manager NEM Real Time Operations
     
127547RESERVE NOTICE15/06/2025 01:15:07 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1730 hrs 15/06/2025 to 1800 hrs 15/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 726 MW.


Manager NEM Real Time Operations
     
127540RESERVE NOTICE14/06/2025 05:15:45 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127539 is cancelled at 1712 hrs 14/06/2025.

Manager NEM Real Time Operations
     
127539RESERVE NOTICE14/06/2025 01:24:29 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1700 hrs 14/06/2025 to 1930 hrs 14/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 691 MW.


Manager NEM Real Time Operations
     
127531MARKET SYSTEMS13/06/2025 10:58:08 AM

Initial - CHG0103468 - Identity Service Site Transfer

Change Number: CHG0103468

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Identity Service (IDS)
Change Title: Identity Service Site Transfer
Change Start Date & Time: 19/06/2025 17:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:39
Outage End Date & Time: 19/06/2025 18:15:00
Environment: Production
Participant Impact and Requirements: Identity Service is used by multiple systems for user authorisation and authentication.
Identity Service is mostly used by the following systems:
*MSATS
*APIs (EMMS, GBB, MSATS)
*WEM
*Internal / Markets Portal Services
Identity Service may cause users to experience outages or few session issues for logins initated between 18:00 to 18:15 Market Time on 19/June/2025.
Internal / Market Portal Services will have an outage due to EMMS site transfer activities carried out in parallel, under a seperate change.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm