Filter by category
Filter by Date
Cancellation - AEMO Intervention Event - SA region 25/07/2025
Cancellation - AEMO Intervention Event - SA region 25/07/2025
Refer to Market Notice 128310
The AEMO Intervention Event and all associated directions are cancelled from 0630 hrs on 28/07/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128380
Direction is cancelled from: 0630 hrs 28/07/2025
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128377
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0630 hrs 28/07/2025.
The direction update is issued at 1630 hrs 27/07/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128318
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 28/07/2025.
The direction update is issued at 1700 hrs 26/07/2025.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 128373
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 26/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1700 hrs 26/07/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 26/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128311
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/07/2025.
The direction update is issued at 1700 hrs 25/07/2025.
Manager NEM Real Time Operations
Initial - CHG0104554 - Production eMDM Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: Production eMDM Maintenance Release
Change Start Date & Time: 03/08/2025 10:00:00
Change End Date & Time: 03/08/2025 14:00:00
Outage Start Date & Time: 03/08/2025 10:00:00
Outage End Date & Time: 03/08/2025 14:00:00
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0400 hrs 26/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations