Filter by category
Filter by Date
[EventId:202507211630_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 July 2025 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 21 July 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 July 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1630 hrs on 21 July 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Planned outage of Dapto - Kangaroo Valley (18) 330 kV line in the NSW region on 20/07/2025
The Dapto - Kangaroo Valley (18) 330 kV line in the New South Wales (NSW) region is planned to be out of service from 0615 hrs to 1630 hrs 20/07/2025.
This outage is considered as a High Impact Outage (HIO).
During this planned outage:
- There is a potential for Energy and FCAS prices to approach the Market Price Cap.
- Power transfer will be restricted between VIC/Snowy and NSW.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
[EventId:202507162215_confirmed] Prices for interval 16-Jul-2025 22:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:15.
In accordance with Market Notice 128139 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507162235_confirmed] Prices for interval 16-Jul-2025 22:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:35.
In accordance with Market Notice 128143 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507162230_confirmed] Prices for interval 16-Jul-2025 22:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:30.
In accordance with Market Notice 128142 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507162225_confirmed] Prices for interval 16-Jul-2025 22:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:25.
In accordance with Market Notice 128141 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507162220_confirmed] Prices for interval 16-Jul-2025 22:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:20.
In accordance with Market Notice 128140 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507162210_confirmed] Prices for interval 16-Jul-2025 22:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025
PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:10.
In accordance with Market Notice 128138 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Network Augmentation Commissioned - NSW Region - 14/07/2025
Network Augmentation Commissioned - NSW Region - 14/07/2025
Commissioned:
Buronga No. 1 330 kV/330 kV phase shifting transformer
Buronga No. 2 330 kV/330 kV phase shifting transformer
Buronga No. 3 330 kV/330 kV phase shifting transformer
Buronga No. 4 330 kV/330 kV phase shifting transformer
Manager NEM Real Time Operations