127623RESERVE NOTICE17/06/2025 08:53:51 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1900 hrs 18/06/2025.
The forecast capacity reserve requirement is 1047 MW.
The minimum capacity reserve available is 957 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127616PRICES SUBJECT TO REVIEW17/06/2025 08:20:16 AM

[EventId:202506170825_review] Prices for interval 17-Jun-2025 08:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 17 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 08:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127615PRICES SUBJECT TO REVIEW17/06/2025 08:15:15 AM

[EventId:202506170820_review] Prices for interval 17-Jun-2025 08:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0815 hrs on 17 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 08:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127614PRICES SUBJECT TO REVIEW17/06/2025 08:10:21 AM

[EventId:202506170815_review] Prices for interval 17-Jun-2025 08:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0810 hrs on 17 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 08:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127613PRICES SUBJECT TO REVIEW17/06/2025 08:05:17 AM

[EventId:202506170810_review] Prices for interval 17-Jun-2025 08:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0805 hrs on 17 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 08:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127612PRICES SUBJECT TO REVIEW17/06/2025 08:00:16 AM

[EventId:202506170805_review] Prices for interval 17-Jun-2025 08:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0800 hrs on 17 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 08:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127611PRICES SUBJECT TO REVIEW17/06/2025 07:55:15 AM

[EventId:202506170800_review] Prices for interval 17-Jun-2025 08:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0755 hrs on 17 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jun-2025 08:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127605RESERVE NOTICE16/06/2025 05:37:52 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 127604 is cancelled at 1700 hrs 16/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127604RESERVE NOTICE16/06/2025 05:12:00 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 0700 hrs to 0830 hrs 18/06/2025.
The forecast capacity reserve requirement is 1086 MW.
The minimum capacity reserve available is 896 MW.

2. From 1630 hrs to 1700 hrs 18/06/2025.
The forecast capacity reserve requirement is 1128 MW.
The minimum capacity reserve available is 922 MW.

3. From 1730 hrs to 1900 hrs 18/06/2025.
The forecast capacity reserve requirement is 1167 MW.
The minimum capacity reserve available is 1135 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     