128135RESERVE NOTICE16/07/2025 05:11:13 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1800 hrs 16/07/2025 to 1900 hrs 16/07/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1343 MW.


Manager NEM Real Time Operations
     
128133NON-CONFORMANCE16/07/2025 07:20:23 AM

NON-CONFORMANCE Region QLD1 Wednesday, 16 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 16 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ULPBESS1
Duration: 16/07/2025 07:10 to 16/07/2025 07:20
Amount: 7 MW
Constraint: NC-Q_ULPBESS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128130MARKET SYSTEMS15/07/2025 01:08:06 PM

Initial - CHG0104670 - Planned system maintenance to the EMMS PreProduction Environment

Change Number: CHG0104670

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Windows Server
Change Title: Planned system maintenance to the EMMS PreProduction Environment
Change Start Date & Time: 17/07/2025 09:00:00
Change End Date & Time: 17/07/2025 17:00:00
Outage Start Date & Time: 17/07/2025 09:00:00
Outage End Date & Time: 17/07/2025 14:00:00
Environment: Pre-Production

Participant Impact and Requirements: The Pre-Production Electricity Market Management System(EMMS) ,Frequency Performance Payments (FPP), Gas Supply Hub (GSH) will be unavailable during the scheduled outage window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
128121MARKET INTERVENTION13/07/2025 04:02:17 PM

Cancellation - AEMO Intervention Event - SA region 12/07/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 12/07/2025

Refer to Market Notice 128101

The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 13/07/2025.


Manager NEM Real Time Operations
     
128120MARKET INTERVENTION13/07/2025 04:02:03 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 128102

Direction is cancelled from: 1600 hrs 13/07/2025

Manager NEM Real Time Operations
     
128119RESERVE NOTICE13/07/2025 01:42:17 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 128118 is cancelled at 1338 hrs 13/07/2025.

Manager NEM Real Time Operations
     
128118RESERVE NOTICE13/07/2025 12:51:15 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 0800 hrs 14/07/2025 to 0930 hrs 14/07/2025.
The forecast capacity reserve requirement is 436 MW.
The minimum capacity reserve available is 325 MW.


Manager NEM Real Time Operations
     
128103MARKET INTERVENTION12/07/2025 02:42:09 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 128097

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 12/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1450 hrs 12/07/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
128102MARKET INTERVENTION12/07/2025 02:51:31 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 128101


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1450 hrs 12/07/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2200 hrs 12/07/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1600 hrs 13/07/2025 .

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     