STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127480 has been updated to the following:
[1.] From 0630 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 654 MW.
The minimum capacity reserve available is 608 MW.
[2.] From 1830 hrs 10/06/2025 to 1930 hrs 10/06/2025.
The forecast capacity reserve requirement is 905 MW.
The minimum capacity reserve available is 895 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127477 has been updated at 1815 hrs to the following:
[1.] From 0630 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 657 MW.
The minimum capacity reserve available is 619 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 127454 has been updated to the following:
[1.] From 0700 hrs 10/06/2025 to 0930 hrs 10/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 885 MW.
[2.] From 1630 hrs 10/06/2025 to 1700 hrs 10/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 1105 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/06/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127402 has been updated to the following:
[1.] From 1700 hrs 12/06/2025 to 2100 hrs 12/06/2025.
The forecast capacity reserve requirement is 1691 MW.
The minimum capacity reserve available is 1532 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127447 has been updated at 1415 hrs to the following:
[1.] From 0600 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 728 MW.
The minimum capacity reserve available is 612 MW.
[2.] From 1830 hrs 10/06/2025 to 1930 hrs 10/06/2025.
The forecast capacity reserve requirement is 919 MW.
The minimum capacity reserve available is 900 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Network Augmentation Commissioned - NSW Region - 07/06/2025
A network augmentation has been commissioned in the NSW region at 2350 hrs 07/06/2025 as follows:
Culcairn Solar Farm substation has been cut into the existing Walla Walla - Wagga 6Y 330 kV Transmission Line to form the following circuits:
Culcairn - Walla Walla 6Y 330 kV Transmission Line
Walla Walla - Wagga 3G 330 kV Transmission Line
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following periods:
From 0730 hrs 10/06/2025 to 0900 hrs 10/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 925 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127435 has been updated at 1145hrs to the following:
From 0600 hrs 10/06/2025 to 0730 hrs 10/06/2025.
The forecast capacity reserve requirement is 832 MW.
The minimum capacity reserve available is 585 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 0630 hrs to 0700 hrs 10/06/2025:
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 585 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations