Market Notices

127842RESERVE NOTICE25/06/2025 12:54:52 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 26/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Periods:


[1.] From 1000 hrs 26/06/2025 to 1030 hrs 26/06/2025.
The forecast capacity reserve requirement is 430 MW.
The minimum capacity reserve available is 416 MW.


[2.] From 1430 hrs 26/06/2025 to 1600 hrs 26/06/2025.
The forecast capacity reserve requirement is 437 MW.
The minimum capacity reserve available is 373 MW.


[3.] From 1730 hrs 26/06/2025 to 2200 hrs 26/06/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 354 MW.


Manager NEM Real Time Operations
     
127841RESERVE NOTICE25/06/2025 12:54:22 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 26/06/2025 to 1900 hrs 26/06/2025.
The forecast capacity reserve requirement is 1784 MW.
The minimum capacity reserve available is 1698 MW.


Manager NEM Real Time Operations
     
127833NON-CONFORMANCE25/06/2025 06:10:17 AM

NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BARRON-2
Duration: 25/06/2025 06:05 to 25/06/2025 06:10
Amount: -25 MW
Constraint: NC-Q_BARRON-2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127802PRICES SUBJECT TO REVIEW24/06/2025 03:10:17 PM

[EventId:202506241515_review] Prices for interval 24-Jun-2025 15:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1510 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127799PRICES SUBJECT TO REVIEW24/06/2025 03:05:17 PM

[EventId:202506241510_review] Prices for interval 24-Jun-2025 15:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127797PRICES SUBJECT TO REVIEW24/06/2025 03:00:24 PM

[EventId:202506241505_review] Prices for interval 24-Jun-2025 15:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127796PRICES SUBJECT TO REVIEW24/06/2025 02:55:11 PM

[EventId:202506241500_review] Prices for interval 24-Jun-2025 15:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1455 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127793RESERVE NOTICE24/06/2025 03:11:48 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127741 has been updated at 1400 hrs 24/06/2025 to the following:

1. From 1100 hrs to 1130 hrs 01/07/2025.
The forecast capacity reserve requirement is 404 MW.
The minimum capacity reserve available is 377 MW.

2. From 1600 hrs to 1630 hrs 01/07/2025.
The forecast capacity reserve requirement is 410 MW.
The minimum capacity reserve available is 301 MW.

AEMO Operations
     
127791PRICES SUBJECT TO REVIEW24/06/2025 02:50:10 PM

[EventId:202506241455_review] Prices for interval 24-Jun-2025 14:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 14:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm