127866SETTLEMENTS RESIDUE25/06/2025 05:20:24 PM

[EventId:202506251720_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 25 June 2025 17:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 25 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 25 June 2025.

Refer to market notice: 127856

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1720 hrs on 25 June 2025.

This is an AEMO autogenerated Market Notice.
     
127864RESERVE NOTICE25/06/2025 04:58:25 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127847 is cancelled at 1600 hrs on 25/06/2025.

No LOR3 condition is currently forecast in the STPASA period.

AEMO Operations
     
127856SETTLEMENTS RESIDUE25/06/2025 03:35:15 PM

[EventId:202506251535_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 25 June 2025 15:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 25 June 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 25 June 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1535 hrs on 25 June 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
127847RESERVE NOTICE25/06/2025 02:48:13 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0630 hrs to 1100 hrs 02/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 108 MW at 0800 hrs.

2. From 1700 hrs 02/07/2025 to 0000 hrs 03/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 153 MW at 1900 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127835MARKET SYSTEMS25/06/2025 09:48:25 AM

CHG0103089 - ERI & STPASA Recall Period Production Release

Change Number: CHG0103089

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release
Change Start Date & Time: 30/06/2025 09:00:00
Change End Date & Time: 04/07/2025 18:00:00
Outage Start Date & Time: 30/06/2025 11:45:00
Outage End Date & Time: 30/06/2025 11:55:00
Environment: Production
Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch, 5-Minute Predispatch, Predispatch, PD7, Bidding, SOMMS and?Registration. This change will become effective upon rule commencement on 1 July, 2025

Impact : A Planned outage for BIDDING application is scheduled on 30th June 2025 between 11:45 AM and 11:55 AM. The application will be unavailable for approximately 5-7 min during this window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127834GENERAL NOTICE25/06/2025 08:54:58 AM

Planned outage of Kiamal SF-Red Cliffs 220kV LINE in the VIC region on 27/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Kiamal SF-Red Cliffs 220kV LINE line in the Victorian (VIC) region is planned to be out of service from 0700 hrs on 27/06/2025 to 1630 hrs on 27/06/2025.

A credible contingency event during this planned outage may require:

* Load shedding in the Victorian outer grid; and/ or
* Market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
127829SETTLEMENTS RESIDUE24/06/2025 09:30:24 PM

[EventId:202506242130_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 June 2025 21:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2130 hrs on 24 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.

Refer to market notice: 127824

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 2130 hrs on 24 June 2025.

This is an AEMO autogenerated Market Notice.
     
127824SETTLEMENTS RESIDUE24/06/2025 08:35:21 PM

[EventId:202506242035_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 June 2025 20:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2035 hrs on 24 June 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 2035 hrs on 24 June 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
127823SETTLEMENTS RESIDUE24/06/2025 08:00:35 PM

[EventId:202506242000_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 June 2025 20:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2000 hrs on 24 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.

Refer to market notice: 127821

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 2000 hrs on 24 June 2025.