128259RESERVE NOTICE22/07/2025 04:34:09 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 25/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0800 hrs to 1000 hrs 25/07/2025.
The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 790 MW.

2. From 1030 hrs to 1130 hrs 25/07/2025.
The forecast capacity reserve requirement is 846 MW.
The minimum capacity reserve available is 798 MW.

3. From 1300 hrs to 1330 hrs 25/07/2025.
The forecast capacity reserve requirement is 842 MW.
The minimum capacity reserve available is 837 MW.

4. From 1400 hrs to 1530 hrs 25/07/2025.
The forecast capacity reserve requirement is 839 MW.
The minimum capacity reserve available is 804 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

AEMO Operations
     
128215NON-CONFORMANCE21/07/2025 06:45:14 PM

NON-CONFORMANCE Region SA1 Monday, 21 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 21 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BLYTHB1
Duration: 21/07/2025 18:40 to 21/07/2025 18:45
Amount: 11 MW
Constraint: NC-S_BLYTHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128209NON-CONFORMANCE20/07/2025 03:55:18 PM

NON-CONFORMANCE Region QLD1 Sunday, 20 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 20 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 20/07/2025 15:45 to 20/07/2025 15:55
Amount: -51 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
     
128175POWER SYSTEM EVENTS19/07/2025 01:35:42 PM

Non-credible contingency event - TAS region - 19/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 19/07/2025

At 1240 hrs the Liapoota - Wadamana - Palmerston 220 kV line and the Cattle Hill Wind Farm - Wadamana 220 kV line tripped.

AEMO did not instruct load shedding.

AEMO has been advised of a 70 MW load reduction at Nyrstar.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
128160POWER SYSTEM EVENTS18/07/2025 08:49:29 AM

Non-credible contingency event - QLD region - 18/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 18/07/2025

At 0825 hrs the H11_Nebo 275/132 kV No.1 Transformer was switched out on a planned outage and the H11_Nebo 275 kV SVC tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
128159NON-CONFORMANCE18/07/2025 06:30:29 AM

NON-CONFORMANCE Region QLD1 Friday, 18 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 18 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: DDPS1
Duration: 18/07/2025 06:25 to 18/07/2025 06:30
Amount: -14 MW
Constraint: NC-Q_DDPS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128137RESERVE NOTICE16/07/2025 07:24:19 PM

Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 128136 is cancelled at 1915 hrs 16/07/2025.

Manager NEM Real Time Operations
     
128136RESERVE NOTICE16/07/2025 06:10:16 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/07/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1257 MW

Manager NEM Real Time Operations
     
128133NON-CONFORMANCE16/07/2025 07:20:23 AM

NON-CONFORMANCE Region QLD1 Wednesday, 16 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 16 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ULPBESS1
Duration: 16/07/2025 07:10 to 16/07/2025 07:20
Amount: 7 MW
Constraint: NC-Q_ULPBESS1

Auto-generated on behalf of Manager NEM Real Time Operations
     