127951RESERVE NOTICE05/07/2025 12:31:16 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 0730 hrs 11/07/2025 to 0900 hrs 11/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 220 MW.

[2.] From 1730 hrs 11/07/2025 to 2200 hrs 11/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 206 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
127950MARKET INTERVENTION05/07/2025 08:16:17 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 127949

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 05/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage

AEMO estimates that, in the absence of sufficient market response by 1400 hrs 05/07/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
127949MARKET INTERVENTION05/07/2025 07:38:36 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 05/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
127948RESERVE NOTICE05/07/2025 05:58:43 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 12/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127940 is cancelled at 0555 hrs 05/07/2025.

Manager NEM Real Time Operations
     
127947RESERVE NOTICE05/07/2025 05:58:33 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in theSA region advised in AEMO Electricity Market Notice No. 127939 is cancelled at 0555 hrs 05/07/2025.

Manager NEM Real Time Operations
     
127946NON-CONFORMANCE04/07/2025 04:45:17 PM

NON-CONFORMANCE Region QLD1 Friday, 4 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 4 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TARONG#3
Duration: 04/07/2025 16:40 to 04/07/2025 16:45
Amount: -18 MW
Constraint: NC-Q_TARONG#3

Auto-generated on behalf of Manager NEM Real Time Operations
     
127940RESERVE NOTICE04/07/2025 01:54:12 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 12/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

1. From 0000 hrs to 0230 hrs 12/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 181 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127939RESERVE NOTICE04/07/2025 01:54:22 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0400 hrs to 1030 hrs 11/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 135 MW.

2. From 1700 hrs to 2359 hrs 11/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 109 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127938MARKET INTERVENTION04/07/2025 04:00:11 PM

Cancellation - AEMO Intervention Event - SA region 03/07/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 03/07/2025

Refer to Market Notice 127928

The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 04/07/2025.