Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 18/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 16/07/2025 to 1900 hrs 16/07/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1343 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 16 July 2025
NON-CONFORMANCE QLD1 Region Wednesday, 16 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: ULPBESS1
Duration: 16/07/2025 07:10 to 16/07/2025 07:20
Amount: 7 MW
Constraint: NC-Q_ULPBESS1
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 14/07/2025
Network Augmentation Commissioned - NSW Region - 14/07/2025
Commissioned:
Buronga No. 1 330 kV/330 kV phase shifting transformer
Buronga No. 2 330 kV/330 kV phase shifting transformer
Buronga No. 3 330 kV/330 kV phase shifting transformer
Buronga No. 4 330 kV/330 kV phase shifting transformer
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 12/07/2025
Cancellation - AEMO Intervention Event - SA region 12/07/2025
Refer to Market Notice 128101
The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 13/07/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128102
Direction is cancelled from: 1600 hrs 13/07/2025
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 128118 is cancelled at 1338 hrs 13/07/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 0800 hrs 14/07/2025 to 0930 hrs 14/07/2025.
The forecast capacity reserve requirement is 436 MW.
The minimum capacity reserve available is 325 MW.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 128097
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 12/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1450 hrs 12/07/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations