Market Notices

127539RESERVE NOTICE14/06/2025 01:24:29 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1700 hrs 14/06/2025 to 1930 hrs 14/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 691 MW.


Manager NEM Real Time Operations
     
127537RESERVE NOTICE14/06/2025 10:51:52 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127536 has been updated at 1012 hrs 14/06/2025 to the following:


[1.] From 0700 hrs 17/06/2025 to 0730 hrs 17/06/2025.
The forecast capacity reserve requirement is 581 MW.
The minimum capacity reserve available is 577 MW.

[2.] From 0800 hrs 17/06/2025 to 0900 hrs 17/06/2025.
The forecast capacity reserve requirement is 562 MW.
The minimum capacity reserve available is 530 MW.

[3.] From 0930 hrs 17/06/2025 to 1000 hrs 17/06/2025.
The forecast capacity reserve requirement is 562 MW.
The minimum capacity reserve available is 559 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
127536RESERVE NOTICE14/06/2025 08:58:13 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 0630 hrs 17/06/2025 to 0800 hrs 17/06/2025.
The forecast capacity reserve requirement is 552 MW.
The minimum capacity reserve available is 514 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
127534RESERVE NOTICE13/06/2025 03:11:22 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127524 is cancelled at 1400 hrs 13/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127533RESERVE NOTICE13/06/2025 03:11:24 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 16/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127532 is cancelled at 1400 hrs 13/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127532RESERVE NOTICE13/06/2025 11:52:07 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 16/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 0900 hrs to 1000 hrs 16/06/2025.
The forecast capacity reserve requirement is 845 MW.
The minimum capacity reserve available is 809 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127531MARKET SYSTEMS13/06/2025 10:58:08 AM

Initial - CHG0103468 - Identity Service Site Transfer

Change Number: CHG0103468

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Identity Service (IDS)
Change Title: Identity Service Site Transfer
Change Start Date & Time: 19/06/2025 17:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:39
Outage End Date & Time: 19/06/2025 18:15:00
Environment: Production
Participant Impact and Requirements: Identity Service is used by multiple systems for user authorisation and authentication.
Identity Service is mostly used by the following systems:
*MSATS
*APIs (EMMS, GBB, MSATS)
*WEM
*Internal / Markets Portal Services
Identity Service may cause users to experience outages or few session issues for logins initated between 18:00 to 18:15 Market Time on 19/June/2025.
Internal / Market Portal Services will have an outage due to EMMS site transfer activities carried out in parallel, under a seperate change.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127530MARKET SYSTEMS13/06/2025 10:53:37 AM

Initial - CHG0103768 - Planned maintenance affecting the AEMO Market Network

Change Number: CHG0103768

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.
Change Start Date & Time: 26/06/2025 07:00:00
Change End Date & Time: 26/06/2025 18:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 26th of June 2025, between 07:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.

During the change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127529MARKET SYSTEMS13/06/2025 10:46:24 AM

Initial - CHG0103783 - Planned maintenance affecting the AEMO Market Network

Change Number: CHG0103783

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.
Change Start Date & Time: 23/06/2025 07:00:15
Change End Date & Time: 23/06/2025 18:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 23rd of June 2025, between 07:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Sydney.

During the change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Sydney as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Brisbane will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Sydney, to switch these connections to the Brisbane site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Brisbane site and do not need to take any action.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm