Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128318
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 28/07/2025.
The direction update is issued at 1700 hrs 26/07/2025.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 128373
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 26/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1700 hrs 26/07/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 26/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 26/07/2025
Update - Non-credible contingency event - NSW region - 26/07/2025
Refer AEMO Electricity Market Notice 128353
At 0832 hrs the Canberra A 132kV Bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 26/07/2025
Non-credible contingency event - NSW region - 26/07/2025
At 0449 hrs the Canberra 132 kV A Bus and the Canberra to Latham A2 132 kV Line tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128311
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/07/2025.
The direction update is issued at 1700 hrs 25/07/2025.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 28/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128313 is cancelled at 1400 hrs 25/07/2025.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0400 hrs 26/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 28/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 0730 hrs to 0900 hrs 28/07/2025.
The forecast capacity reserve requirement is 563 MW.
The minimum capacity reserve available is 536 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations