127600RESERVE NOTICE16/06/2025 02:12:27 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127598 is cancelled at 1410 hrs 16/06/2025.

Manager NEM Real Time Operations
     
127599RESERVE NOTICE16/06/2025 01:28:23 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1700 hrs 17/06/2025 to 1730 hrs 17/06/2025.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 389 MW.

[2.] From 1800 hrs 17/06/2025 to 2130 hrs 17/06/2025.
The forecast capacity reserve requirement is 633 MW.
The minimum capacity reserve available is 478 MW.

Manager NEM Real Time Operations
     
127598RESERVE NOTICE16/06/2025 01:23:01 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 1730 hrs 17/06/2025 to 1800 hrs 17/06/2025.
The forecast capacity reserve requirement is 292 MW.
The minimum capacity reserve available is 230 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
127597RESERVE NOTICE16/06/2025 12:31:23 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127577 is cancelled at 1200 hrs 16/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127579RESERVE NOTICE16/06/2025 10:39:32 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127576 is cancelled at 1000 hrs 16/06/2025.

AEMO Operations
     
127577RESERVE NOTICE16/06/2025 09:45:46 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127561 has been updated at 0900 hrs 16/06/2025 to the following:

1. From 1000 hrs to 1130 hrs 17/06/2025.
The forecast capacity reserve requirement is 706 MW.
The minimum capacity reserve available is 489 MW.

2. From 1400 hrs to 1430 hrs 17/06/2025.
The forecast capacity reserve requirement is 697 MW.
The minimum capacity reserve available is 514 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127576RESERVE NOTICE16/06/2025 09:45:50 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127575 has been updated at 0900 hrs 16/06/2025 to the following:

From 1700 hrs to 1800 hrs 17/06/2025.
The forecast capacity reserve requirement is 314 MW.
The minimum capacity reserve available is 297 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127575RESERVE NOTICE16/06/2025 08:54:04 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 17/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127571 has been updated at 0800 hrs 16/06/2025 to the following:

1. From 0730 hrs to 0930 hrs 17/06/2025.
The forecast capacity reserve requirement is 313 MW.
The minimum capacity reserve available is 282 MW.

2. From 1500 hrs 17/06/2025 to 1800 hrs 17/06/2025.
The forecast capacity reserve requirement is 313 MW.
The minimum capacity reserve available is 290 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127573RESERVE NOTICE16/06/2025 07:15:27 AM

Cancellation of Actual (LOR1) condition in the QLD region - 16/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 16/06/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127572 is cancelled at 0715 hrs 16/06/2025.

Manager NEM Real Time Operations
     