127488RESERVE NOTICE09/06/2025 01:47:38 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 127487 is cancelled at 1345 hrs 09/06/2025.

Manager NEM Real Time Operations
     
127487RESERVE NOTICE09/06/2025 12:48:11 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:


[1.] From 0800 hrs 10/06/2025 to 0900 hrs 10/06/2025.
The forecast capacity reserve requirement is 1166 MW.
The minimum capacity reserve available is 840 MW.


Manager NEM Real Time Operations
     
127486RESERVE NOTICE09/06/2025 01:48:41 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127481 is cancelled at 01:15 hrs. 09/06/2025.

Manager NEM Real Time Operations
     
127485RESERVE NOTICE09/06/2025 01:47:20 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127482 is cancelled at 01:15 hrs. 09/06/2025.

Manager NEM Real Time Operations
     
127484MARKET SYSTEMS09/06/2025 01:25:11 AM

INC0145687 - RESOLVED - Frequency Performance Payments (FPP) System

INC0145687 - RESOLVED - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - RESOLVED

The service interruption relating to Frequency Performance Payments (FPP) System has been resolved.

The FPP System started normal operations from 00:25 Hrs AEST on 09/06/2025

Default Contribution Factors (DCFs) will be used for Regulation Frequency Control Ancillary Service (FCAS) recovery for the trading intervals where CFs were not calculated. No FPP amount will be paid or due for those Trading Intervals.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au

AEMO IT Duty Manager
     
127483MARKET SYSTEMS09/06/2025 12:02:59 AM

INC0145687 - ALERT - Frequency Performance Payments (FPP) Syste

INC0145687 - ALERT - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

AEMO is experiencing a service interruption relating to Frequency Performance Payments (FPP) System.

The service interruption started from 20:25 hrs AEST on 08/06/2025. The participants will experience a delay in receiving FPP factors.

AEMO is working on resolving the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au


































     
127482RESERVE NOTICE08/06/2025 07:25:26 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1800 hrs 11/06/2025 to 1900 hrs 11/06/2025.
The forecast capacity reserve requirement is 881 MW.
The minimum capacity reserve available is 856 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
127481RESERVE NOTICE08/06/2025 07:24:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127480 has been updated to the following:

[1.] From 0630 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 654 MW.
The minimum capacity reserve available is 608 MW.

[2.] From 1830 hrs 10/06/2025 to 1930 hrs 10/06/2025.
The forecast capacity reserve requirement is 905 MW.
The minimum capacity reserve available is 895 MW.

AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
127480RESERVE NOTICE08/06/2025 06:18:03 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127477 has been updated at 1815 hrs to the following:

[1.] From 0630 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 657 MW.
The minimum capacity reserve available is 619 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.