Market Notices

127551MARKET INTERVENTION15/06/2025 06:53:11 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2300 hrs 15/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
127550MARKET INTERVENTION15/06/2025 04:00:22 AM

Cancellation - AEMO Intervention Event - SA region 12/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 12/06/2025

Refer to Market Notice 127518

The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 15/06/2025.


Manager NEM Real Time Operations
     
127549MARKET INTERVENTION15/06/2025 04:00:09 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127535

Direction is cancelled from: 0400 hrs 15/06/2025

Manager NEM Real Time Operations
     
127548RESERVE NOTICE15/06/2025 01:50:06 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127547 is cancelled at 0140 hrs 15/06/2025.

Manager NEM Real Time Operations
     
127547RESERVE NOTICE15/06/2025 01:15:07 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1730 hrs 15/06/2025 to 1800 hrs 15/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 726 MW.


Manager NEM Real Time Operations
     
127543RESERVE NOTICE14/06/2025 06:10:33 PM

Cancellation of Actual (LOR1) condition in the QLD region - 14/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 14/06/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127542 is cancelled at 1808 hrs 14/06/2025.

Manager NEM Real Time Operations
     
127542RESERVE NOTICE14/06/2025 05:41:52 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 724 MW

Manager NEM Real Time Operations
     
127540RESERVE NOTICE14/06/2025 05:15:45 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127539 is cancelled at 1712 hrs 14/06/2025.

Manager NEM Real Time Operations
     
127539RESERVE NOTICE14/06/2025 01:24:29 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1700 hrs 14/06/2025 to 1930 hrs 14/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 691 MW.


Manager NEM Real Time Operations
     