128163MARKET INTERVENTION18/07/2025 12:11:23 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 128154

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 18/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 18/07/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
128161MARKET SYSTEMS18/07/2025 10:04:13 AM

Initial - CHG0104553 - Pre-Prod eMDM Maintenance Release

Change Number: CHG0104553

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release
Change Start Date & Time: 21/07/2025 13:00:00
Change End Date & Time: 21/07/2025 17:00:00
Outage Start Date & Time: 21/07/2025 13:00:00
Outage End Date & Time: 21/07/2025 17:00:00
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
128154MARKET INTERVENTION17/07/2025 06:42:08 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 18/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
128135RESERVE NOTICE16/07/2025 05:11:13 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1800 hrs 16/07/2025 to 1900 hrs 16/07/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1343 MW.


Manager NEM Real Time Operations
     
128130MARKET SYSTEMS15/07/2025 01:08:06 PM

Initial - CHG0104670 - Planned system maintenance to the EMMS PreProduction Environment

Change Number: CHG0104670

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Windows Server
Change Title: Planned system maintenance to the EMMS PreProduction Environment
Change Start Date & Time: 17/07/2025 09:00:00
Change End Date & Time: 17/07/2025 17:00:00
Outage Start Date & Time: 17/07/2025 09:00:00
Outage End Date & Time: 17/07/2025 14:00:00
Environment: Pre-Production

Participant Impact and Requirements: The Pre-Production Electricity Market Management System(EMMS) ,Frequency Performance Payments (FPP), Gas Supply Hub (GSH) will be unavailable during the scheduled outage window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
128121MARKET INTERVENTION13/07/2025 04:02:17 PM

Cancellation - AEMO Intervention Event - SA region 12/07/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 12/07/2025

Refer to Market Notice 128101

The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 13/07/2025.


Manager NEM Real Time Operations
     
128120MARKET INTERVENTION13/07/2025 04:02:03 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 128102

Direction is cancelled from: 1600 hrs 13/07/2025

Manager NEM Real Time Operations
     
128119RESERVE NOTICE13/07/2025 01:42:17 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 128118 is cancelled at 1338 hrs 13/07/2025.

Manager NEM Real Time Operations
     
128118RESERVE NOTICE13/07/2025 12:51:15 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 0800 hrs 14/07/2025 to 0930 hrs 14/07/2025.
The forecast capacity reserve requirement is 436 MW.
The minimum capacity reserve available is 325 MW.


Manager NEM Real Time Operations
     