Initial - CHG0102957 - Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1
Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1
Change Start Date & Time: 03/08/2025 10:00:00
Change End Date & Time: 03/08/2025 14:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The Gas B2B hub servers will be updated to support TLS (Transport Layer Security) 1.3 version. Also the legacy versions 1.0 and 1.1 will be disabled and not be supported going forward. Participants are required to use TLS 1.2 as a minimum protocol to communicate with AEMO, failing to do so will impact the connectivity. An outage is not expected but, there may be some minor interruptions during the change period.
Participants are required to make sure the connectivity is intact post change implementation. In case of any issues noticed, please reach out to AEMO Support Hub.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Initial - CHG0104481 - Update Shareplex NuTCracker resource allocation
Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: Update Shareplex NuTCracker resource allocation
Change Start Date & Time: 08/07/2025 10:00:00
Change End Date & Time: 08/07/2025 17:00:00
Outage Start Date & Time: 08/07/2025 10:00:00
Outage End Date & Time: 08/07/2025 12:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Pre-Production Electricity Market Management System(EMMS) ,Frequency Performance Payments (FPP) ,Gas Supply Hub (GSH) will be unavailable during the scheduled outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
CHG0103089 - ERI & STPASA Recall Period Production Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0104394 - Planned maintenance affecting the AEMO Market Network.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.
Change Start Date & Time: 09/07/2025 07:00:00
Change End Date & Time: 09/07/2025 17:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 9th of July 2025, between 07:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.
During the change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this period. AEMO recommends that all market participants with site-to-site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.
Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
CHG0103089 - ERI & STPASA Recall Period Production Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release
Change Start Date & Time: 30/06/2025 09:00:00
Change End Date & Time: 04/07/2025 18:00:00
Outage Start Date & Time: 30/06/2025 11:45:00
Outage End Date & Time: 30/06/2025 11:55:00
Environment: Production
Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch, 5-Minute Predispatch, Predispatch, PD7, Bidding, SOMMS and?Registration. This change will become effective upon rule commencement on 1 July, 2025
Impact : A Planned outage for BIDDING application is scheduled on 30th June 2025 between 11:45 AM and 11:55 AM. The application will be unavailable for approximately 5-7 min during this window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
CHG0103089 - ERI & STPASA Recall Period Production Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release
Change Start Date & Time: 30/06/2025 09:00:00
Change End Date & Time: 04/07/2025 18:00:00
Outage Start Date & Time: 30/06/2025 11:45:00
Outage End Date & Time: 30/06/2025 11:55:00
Environment: Production
Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch, 5-Minute Predispatch, Predispatch, PD7, Bidding, SOMMS and?Registration. This change will become effective upon rule commencement on 1 July, 2025
Impact : A Planned outage for BIDDING application is scheduled on 30th June 2025 between 11:45 AM and 11:55 AM. The application will be unavailable for approximately 5-7 min during this window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
[EventId:202506241515_review] Prices for interval 24-Jun-2025 15:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241510_review] Prices for interval 24-Jun-2025 15:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241505_review] Prices for interval 24-Jun-2025 15:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.