Filter by category
Filter by Date
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127847 is cancelled at 1600 hrs on 25/06/2025.
No LOR3 condition is currently forecast in the STPASA period.
AEMO Operations
Cancellation of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: VIC1
Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV
Cancellation time: 25/06/2025 16:34
Constraint set(s) revoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 127855
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 01/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following periods:
From 0000 hrs to 0030 hrs 01/07/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 1010 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
From 0330 hrs to 0400 hrs 03/07/2025.
The forecast capacity reserve requirement is 467 MW.
The minimum capacity reserve available is 253 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 1130 hrs to 1300 hrs 02/07/2025.
The forecast capacity reserve requirement is 423 MW.
The minimum capacity reserve available is 269 MW.
2. From 1530 hrs to 1630 hrs 02/07/2025.
The forecast capacity reserve requirement is 437 MW.
The minimum capacity reserve available is 391 MW.
AEMO Operations
Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV
Duration: 25/06/2025 15:29 until further notice
Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 30/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following periods:
1. From 0630 hrs to 1230 hrs 30/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 766 MW.
2. From 1430 hrs to 2359 hrs 30/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 739 MW.
AEMO Operations
STPASA - Update to the forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/06/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127787 has been updated at 1500 hrs 25/06/2025 to the following:
1. From 0600 hrs to 1000 hrs 30/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 828 MW.
2. From 1500 hrs to 2359 hrs 30/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 828 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0630 hrs to 1100 hrs 02/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 108 MW at 0800 hrs.
2. From 1700 hrs 02/07/2025 to 0000 hrs 03/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 153 MW at 1900 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations