Inter-regional transfer limit variation - South_East N 275kV BUS- SA region - 27/07/2025
Inter-regional transfer limit variation - South_East N 275kV BUS - SA region - 27/07/2025
A planned outage of South_East N 275kV BUS in the SA region was scheduled from 0730 hrs 23/07/2025 to 1730 hrs 27/07/2025.
The outage has been completed and South_East N 275kV BUSt returned to service at 1100 hrs 27/07/2025
Constraint set(s) revoked: S-SECB6611_10
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 26 July 2025
NON-CONFORMANCE QLD1 Region Saturday, 26 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: ULPBESS1
Duration: 26/07/2025 21:15 to 26/07/2025 21:25
Amount: 6 MW
Constraint: NC-Q_ULPBESS1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 26 July 2025
NON-CONFORMANCE VIC1 Region Saturday, 26 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: KESSB1
Duration: 26/07/2025 13:40 to 26/07/2025 14:05
Amount: 55 MW
Constraint: NC-V_KESSB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 26 July 2025
NON-CONFORMANCE VIC1 Region Saturday, 26 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: RANGEB1
Duration: 26/07/2025 12:45 to 26/07/2025 13:00
Amount: 102 MW
Constraint: NC-V_RANGEB1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 26/07/2025
Update - Non-credible contingency event - NSW region - 26/07/2025
Refer AEMO Electricity Market Notice 128353
At 0832 hrs the Canberra A 132kV Bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 26/07/2025
Non-credible contingency event - NSW region - 26/07/2025
At 0449 hrs the Canberra 132 kV A Bus and the Canberra to Latham A2 132 kV Line tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Monday, 21 July 2025
NON-CONFORMANCE SA1 Region Monday, 21 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BLYTHB1
Duration: 21/07/2025 18:40 to 21/07/2025 18:45
Amount: 11 MW
Constraint: NC-S_BLYTHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 20 July 2025
NON-CONFORMANCE QLD1 Region Sunday, 20 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SWAN_E
Duration: 20/07/2025 15:45 to 20/07/2025 15:55
Amount: -51 MW
Constraint: NC-Q_SWAN_E
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Eraring 500kV - Kemps Creek 5A2 500kV Line - NSW region - 19/07/2025
Inter-regional transfer limit variation - Eraring500kV - Kemps Creek 5A2 500kV Line - NSW region - 19/07/2025
At 1910 hrs 19/07/2025 there was a short notice outage of Eraring 500kV - Kemps Creek 5A2 500kV Line .
The following constraint set(s) invoked at 1920 hrs 19/07/2025
N-ERKC_ONE
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations