Planned outage of Moorabool - Cressy No 1 500 kV line in the VIC region on 19/06/2025
The Moorabool - Cressy No 1 500 kV line in the Victoria (VIC) region is planned to be out of service from 0600 hrs to 1700 hrs on 19/06/2025.
A credible contingency event during this planned outage could cause synchronous separation of the South Australia (SA) region from the rest of the NEM.
During this planned outage:
* Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
* Post contingent FCAS will be sourced within SA following Separation event.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
[EventId:202506161145_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 June 2025 11:45
Issued by Australian Energy Market Operator Ltd at 1145 hrs on 16 June 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.
Refer to market notice: 127594
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1145 hrs on 16 June 2025.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region VIC1 Monday, 16 June 2025
NON-CONFORMANCE VIC1 Region Monday, 16 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MOKOSF1
Duration: 16/06/2025 11:20 to 16/06/2025 11:30
Amount: 30 MW
Constraint: NC-V_MOKOSF1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202506161105_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 June 2025 11:05
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 16 June 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1105 hrs on 16 June 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region VIC1 Monday, 16 June 2025
NON-CONFORMANCE VIC1 Region Monday, 16 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MOKOSF1
Duration: 16/06/2025 10:15 to 16/06/2025 10:45
Amount: 12 MW
Constraint: NC-V_MOKOSF1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202506161030_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 June 2025 10:30
Issued by Australian Energy Market Operator Ltd at 1030 hrs on 16 June 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.
Refer to market notice: 127578
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1030 hrs on 16 June 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202506160935_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 June 2025 09:35
Issued by Australian Energy Market Operator Ltd at 0935 hrs on 16 June 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0935 hrs on 16 June 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Saturday, 14 June 2025
NON-CONFORMANCE QLD1 Region Saturday, 14 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YARANSF1
Duration: 14/06/2025 11:10 to 14/06/2025 12:05
Amount: 67 MW
Constraint: NC-Q_YARANSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 13 June 2025
NON-CONFORMANCE NSW1 Region Friday, 13 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CAPBES1
Duration: 13/06/2025 03:35 to 13/06/2025 04:00
Amount: -35 MW
Constraint: NC-N_CAPBES1
Auto-generated on behalf of Manager NEM Real Time Operations