Cancellation- Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025
Cancellation- Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025
Refer AEMO Electricity Market Notice 127501
In order to maintain the power system in a secure operating state in the NSW region, AEMO invoked automated constraint set CA_SYDS_575BC182 from 1755 hrs until 1810 hrs.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_575BC182 from 1755 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 11/06/2025
Update - Non-credible contingency event - QLD region - 11/06/2025
Refer AEMO Electricity Market Notice 127499
At 1713 hrs the Belmont (H3) No.1 275 kV bus and Loganlea - Belmont (829) 275 kV line tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 11/06/2025
Non-credible contingency event - QLD region - 11/06/2025
At 1713 hrs the Belmont (H3) No.1 275 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector - Yass (3L) 330kV line - NSW region - 11/06/2025
Inter-regional transfer limit variation - Collector - Yass (3L) 330kV line - NSW region - 11/06/2025
A planned outage of Collector - Yass (3L) 330kV line in the NSW region was scheduled from 0700 hrs 10/06/2025 to 1500 hrs 16/06/2025.
The outage has been completed and Collector - Yass (3L) 330kV line returned to service at 1611 hrs 11/06/2025
Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE- QLD region - 10/06/2025
Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE - QLD region - 10/06/2025
At 1000 hrs 10/06/2025 there was a short notice outage of Middle Ridge - Greenbank (8848) 275 kV LINE.
The following constraint set(s) invoked at 1030 hrs 10/06/2025
Q-MRGB_8848_8849
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 07/06/2025
A network augmentation has been commissioned in the NSW region at 2350 hrs 07/06/2025 as follows:
Culcairn Solar Farm substation has been cut into the existing Walla Walla - Wagga 6Y 330 kV Transmission Line to form the following circuits:
Culcairn - Walla Walla 6Y 330 kV Transmission Line
Walla Walla - Wagga 3G 330 kV Transmission Line
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Refer AEMO Electricity Market Notice 127439
AEMO has been notified that the controls to vary Murraylink output are now available.
Constraint set I-CTRL_ISSUE_ML revoked at 1150 hrs.
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).
Refer AEMO Electricity Market Notice 127438
AEMO has been notified that the controls to vary Directlink output are now available.
Constraint set I-CTRL_ISSUE_TE revoked at 1150 hrs.
Manager NEM Real Time Operations