Filter by category
Filter by Date
[EventId:202506071130_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 07 June 2025 11:30
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 7 June 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 7 June 2025.
Refer to market notice: 127445
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1130 hrs on 7 June 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202506071035_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 07 June 2025 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 7 June 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 7 June 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1035 hrs on 7 June 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202506061800_review] Prices for interval 06-Jun-2025 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506061755_review] Prices for interval 06-Jun-2025 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506061750_review] Prices for interval 06-Jun-2025 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506061745_review] Prices for interval 06-Jun-2025 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506061740_review] Prices for interval 06-Jun-2025 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506061735_review] Prices for interval 06-Jun-2025 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 06/06/2025 to 1800 hrs 06/06/2025.
The forecast capacity reserve requirement is 1598 MW.
The minimum capacity reserve available is 1551 MW.
Manager NEM Real Time Operations