128130MARKET SYSTEMS15/07/2025 01:08:06 PM

Initial - CHG0104670 - Planned system maintenance to the EMMS PreProduction Environment

Change Number: CHG0104670

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Windows Server
Change Title: Planned system maintenance to the EMMS PreProduction Environment
Change Start Date & Time: 17/07/2025 09:00:00
Change End Date & Time: 17/07/2025 17:00:00
Outage Start Date & Time: 17/07/2025 09:00:00
Outage End Date & Time: 17/07/2025 14:00:00
Environment: Pre-Production

Participant Impact and Requirements: The Pre-Production Electricity Market Management System(EMMS) ,Frequency Performance Payments (FPP), Gas Supply Hub (GSH) will be unavailable during the scheduled outage window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
128128GENERAL NOTICE14/07/2025 01:43:14 PM

Network Augmentation Commissioned - NSW Region - 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 14/07/2025

Commissioned:
Buronga No. 1 330 kV/330 kV phase shifting transformer
Buronga No. 2 330 kV/330 kV phase shifting transformer
Buronga No. 3 330 kV/330 kV phase shifting transformer
Buronga No. 4 330 kV/330 kV phase shifting transformer

Manager NEM Real Time Operations
     
128121MARKET INTERVENTION13/07/2025 04:02:17 PM

Cancellation - AEMO Intervention Event - SA region 12/07/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 12/07/2025

Refer to Market Notice 128101

The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 13/07/2025.


Manager NEM Real Time Operations
     
128120MARKET INTERVENTION13/07/2025 04:02:03 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 128102

Direction is cancelled from: 1600 hrs 13/07/2025

Manager NEM Real Time Operations
     
128119RESERVE NOTICE13/07/2025 01:42:17 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 128118 is cancelled at 1338 hrs 13/07/2025.

Manager NEM Real Time Operations
     
128118RESERVE NOTICE13/07/2025 12:51:15 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 0800 hrs 14/07/2025 to 0930 hrs 14/07/2025.
The forecast capacity reserve requirement is 436 MW.
The minimum capacity reserve available is 325 MW.


Manager NEM Real Time Operations
     
128117PRICES UNCHANGED13/07/2025 10:30:28 AM

[EventId:202507131010_confirmed] Prices for interval 13-Jul-2025 10:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 13 July 2025

PRICES ARE NOW CONFIRMED for trading interval 13-Jul-2025 10:10.

In accordance with Market Notice 128107 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
128116PRICES UNCHANGED13/07/2025 10:30:27 AM

[EventId:202507131030_confirmed] Prices for interval 13-Jul-2025 10:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 13 July 2025

PRICES ARE NOW CONFIRMED for trading interval 13-Jul-2025 10:30.

In accordance with Market Notice 128111 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
128115PRICES UNCHANGED13/07/2025 10:30:27 AM

[EventId:202507131025_confirmed] Prices for interval 13-Jul-2025 10:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 13 July 2025

PRICES ARE NOW CONFIRMED for trading interval 13-Jul-2025 10:25.

In accordance with Market Notice 128110 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.