127747MARKET INTERVENTION23/06/2025 07:09:33 PM

Cancellation - Direction - NSW region - 23/06/2025

AEMO ELECTRICITY PARTICIPANT NOTICE

Cancellation - Direction - NSW region - 23/06/2025

Refer to Market Notice 127745.

The requirement for AEMO to issue a direction to maintain the power system in a secure operating state has ended. All associated directions are cancelled from 1907hrs on 23/06/2025.

Manager NEM Real Time Operations
     
127745MARKET INTERVENTION23/06/2025 06:00:38 PM

Direction - NSW region 23/06/2025

AEMO ELECTRICITY MARKET NOTICE.

Direction - NSW region 23/06/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the NSW region.

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided.

A further market notice will be issued when all directions related to this requirement have been cancelled.

For the purposes of the National Electricity Rules this was a clause 4.8.9 instruction under clause 4.8.9(a).


Manager NEM Real Time Operations
     
127741RESERVE NOTICE23/06/2025 03:01:39 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0230 hrs to 0400 hrs 01/07/2025.
The forecast capacity reserve requirement is 460 MW.
The minimum capacity reserve available is 230 MW.

AEMO Operations
     
127740MARKET INTERVENTION23/06/2025 02:59:49 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127696

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/06/2025.

The direction update is issued at 1500 hrs 23/06/2025.

Manager NEM Real Time Operations
     
127739RESERVE NOTICE23/06/2025 03:01:19 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0700 hrs to 0730 hrs 30/06/2025.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 350 MW.

2. From 1000 hrs to 1030 hrs 30/06/2025.
The forecast capacity reserve requirement is 406 MW.
The minimum capacity reserve available is 334 MW.

3. From 1630 hrs to 1700 hrs 30/06/2025.
The forecast capacity reserve requirement is 459 MW.
The minimum capacity reserve available is 230 MW.

AEMO Operations
     
127738RESERVE NOTICE23/06/2025 03:00:49 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 0630 hrs to 0800 hrs 26/06/2025.
The forecast capacity reserve requirement is 1859 MW.
The minimum capacity reserve available is 1515 MW.

2. From 1630 hrs to 2230 hrs 26/06/2025.
The forecast capacity reserve requirement is 1859 MW.
The minimum capacity reserve available is 1381 MW.

AEMO Operations
     
127737PRICES UNCHANGED23/06/2025 02:10:20 PM

[EventId:202506231350_confirmed] Prices for interval 23-Jun-2025 13:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1410 hrs on 23 June 2025

PRICES ARE NOW CONFIRMED for trading interval 23-Jun-2025 13:50.

In accordance with Market Notice 127725 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127736PRICES UNCHANGED23/06/2025 02:10:19 PM

[EventId:202506231410_confirmed] Prices for interval 23-Jun-2025 14:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1410 hrs on 23 June 2025

PRICES ARE NOW CONFIRMED for trading interval 23-Jun-2025 14:10.

In accordance with Market Notice 127731 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127735PRICES UNCHANGED23/06/2025 02:10:19 PM

[EventId:202506231405_confirmed] Prices for interval 23-Jun-2025 14:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1410 hrs on 23 June 2025

PRICES ARE NOW CONFIRMED for trading interval 23-Jun-2025 14:05.

In accordance with Market Notice 127730 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     