127847RESERVE NOTICE25/06/2025 02:48:13 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0630 hrs to 1100 hrs 02/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 108 MW at 0800 hrs.

2. From 1700 hrs 02/07/2025 to 0000 hrs 03/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 153 MW at 1900 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127846RESERVE NOTICE25/06/2025 01:44:52 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 26/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127842 is cancelled at 1345 hrs 25/06/2025.

Manager NEM Real Time Operations
     
127845RESERVE NOTICE25/06/2025 01:44:05 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127841 is cancelled at 1345 hrs 25/06/2025.

Manager NEM Real Time Operations
     
127842RESERVE NOTICE25/06/2025 12:54:52 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 26/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Periods:


[1.] From 1000 hrs 26/06/2025 to 1030 hrs 26/06/2025.
The forecast capacity reserve requirement is 430 MW.
The minimum capacity reserve available is 416 MW.


[2.] From 1430 hrs 26/06/2025 to 1600 hrs 26/06/2025.
The forecast capacity reserve requirement is 437 MW.
The minimum capacity reserve available is 373 MW.


[3.] From 1730 hrs 26/06/2025 to 2200 hrs 26/06/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 354 MW.


Manager NEM Real Time Operations
     
127841RESERVE NOTICE25/06/2025 12:54:22 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 26/06/2025 to 1900 hrs 26/06/2025.
The forecast capacity reserve requirement is 1784 MW.
The minimum capacity reserve available is 1698 MW.


Manager NEM Real Time Operations
     
127835MARKET SYSTEMS25/06/2025 09:48:25 AM

CHG0103089 - ERI & STPASA Recall Period Production Release

Change Number: CHG0103089

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release
Change Start Date & Time: 30/06/2025 09:00:00
Change End Date & Time: 04/07/2025 18:00:00
Outage Start Date & Time: 30/06/2025 11:45:00
Outage End Date & Time: 30/06/2025 11:55:00
Environment: Production
Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch, 5-Minute Predispatch, Predispatch, PD7, Bidding, SOMMS and?Registration. This change will become effective upon rule commencement on 1 July, 2025

Impact : A Planned outage for BIDDING application is scheduled on 30th June 2025 between 11:45 AM and 11:55 AM. The application will be unavailable for approximately 5-7 min during this window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127793RESERVE NOTICE24/06/2025 03:11:48 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127741 has been updated at 1400 hrs 24/06/2025 to the following:

1. From 1100 hrs to 1130 hrs 01/07/2025.
The forecast capacity reserve requirement is 404 MW.
The minimum capacity reserve available is 377 MW.

2. From 1600 hrs to 1630 hrs 01/07/2025.
The forecast capacity reserve requirement is 410 MW.
The minimum capacity reserve available is 301 MW.

AEMO Operations
     
127789RESERVE NOTICE24/06/2025 03:11:38 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127739 has been updated at 1400 hrs 24/06/2025 to the following:

1. From 0600 hrs to 0700 hrs 30/06/2025.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 473 MW.

2. From 1030 hrs to 1100 hrs 30/06/2025.
The forecast capacity reserve requirement is 376 MW.
The minimum capacity reserve available is 268 MW.

3. From 1630 hrs to 1700 hrs 30/06/2025.
The forecast capacity reserve requirement is 397 MW.
The minimum capacity reserve available is 200 MW.

AEMO Operations
     
127787RESERVE NOTICE24/06/2025 03:11:28 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 0630 hrs to 0830 hrs 30/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1123 MW.

2. From 1630 hrs to 2300 hrs 30/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1073 MW.

AEMO Operations
     