Filter by category
Filter by Date
[EventId:202506071600_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 07 June 2025 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 7 June 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 7 June 2025.
Refer to market notice: 127457
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1600 hrs on 7 June 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202506071505_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 07 June 2025 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 7 June 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 7 June 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1505 hrs on 7 June 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following periods:
From 0730 hrs 10/06/2025 to 0900 hrs 10/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 925 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127435 has been updated at 1145hrs to the following:
From 0600 hrs 10/06/2025 to 0730 hrs 10/06/2025.
The forecast capacity reserve requirement is 832 MW.
The minimum capacity reserve available is 585 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202506071130_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 07 June 2025 11:30
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 7 June 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 7 June 2025.
Refer to market notice: 127445
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1130 hrs on 7 June 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202506071035_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 07 June 2025 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 7 June 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 7 June 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1035 hrs on 7 June 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 0630 hrs to 0700 hrs 10/06/2025:
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 585 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 06/06/2025 to 1800 hrs 06/06/2025.
The forecast capacity reserve requirement is 1598 MW.
The minimum capacity reserve available is 1551 MW.
Manager NEM Real Time Operations
Completed - CHG0103213 - Scheduled maintenance of Marketnet router in Brisbane
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Scheduled maintenance of Marketnet router in Brisbane
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.