Planned outage of Dapto - Kangaroo Valley (18) 330 kV line in the NSW region on 20/07/2025
The Dapto - Kangaroo Valley (18) 330 kV line in the New South Wales (NSW) region is planned to be out of service from 0615 hrs to 1630 hrs 20/07/2025.
This outage is considered as a High Impact Outage (HIO).
During this planned outage:
- There is a potential for Energy and FCAS prices to approach the Market Price Cap.
- Power transfer will be restricted between VIC/Snowy and NSW.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
Initial - CHG0104553 - Pre-Prod eMDM Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release
Change Start Date & Time: 21/07/2025 13:00:00
Change End Date & Time: 21/07/2025 17:00:00
Outage Start Date & Time: 21/07/2025 13:00:00
Outage End Date & Time: 21/07/2025 17:00:00
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Non-credible contingency event - QLD region - 18/07/2025
Non-credible contingency event - QLD region - 18/07/2025
At 0825 hrs the H11_Nebo 275/132 kV No.1 Transformer was switched out on a planned outage and the H11_Nebo 275 kV SVC tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Initial - CHG0104670 - Planned system maintenance to the EMMS PreProduction Environment
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Windows Server
Change Title: Planned system maintenance to the EMMS PreProduction Environment
Change Start Date & Time: 17/07/2025 09:00:00
Change End Date & Time: 17/07/2025 17:00:00
Outage Start Date & Time: 17/07/2025 09:00:00
Outage End Date & Time: 17/07/2025 14:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Pre-Production Electricity Market Management System(EMMS) ,Frequency Performance Payments (FPP), Gas Supply Hub (GSH) will be unavailable during the scheduled outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Network Augmentation Commissioned - NSW Region - 14/07/2025
Network Augmentation Commissioned - NSW Region - 14/07/2025
Commissioned:
Buronga No. 1 330 kV/330 kV phase shifting transformer
Buronga No. 2 330 kV/330 kV phase shifting transformer
Buronga No. 3 330 kV/330 kV phase shifting transformer
Buronga No. 4 330 kV/330 kV phase shifting transformer
Manager NEM Real Time Operations
Completed - CHG0104394 - Planned maintenance affecting the AEMO Market Network.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Completed - CHG0104582 - Pre-Prod eMDM Maintenance Release
Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Electricity Market Management System_PreProd
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System_PreProd
Change Title: Update Shareplex NuTCracker resource allocation
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Pre-Prod eMDM Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release
Change Start Date & Time: 09/07/2025 13:00:00
Change End Date & Time: 09/07/2025 17:00:00
Outage Start Date & Time: 09/07/2025 13:00:00
Outage End Date & Time: 09/07/2025 17:00:00
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.