127505RESERVE NOTICE11/06/2025 07:43:29 PM

Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the QLD Region on 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127504 is cancelled at 1945 hrs 11/06/2025.

Manager NEM Real Time Operations
     
127504RESERVE NOTICE11/06/2025 07:12:10 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1900 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 693 MW

Manager NEM Real Time Operations
     
127503INTER-REGIONAL TRANSFER11/06/2025 06:24:21 PM

Cancellation- Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation- Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025

Refer AEMO Electricity Market Notice 127501

In order to maintain the power system in a secure operating state in the NSW region, AEMO invoked automated constraint set CA_SYDS_575BC182 from 1755 hrs until 1810 hrs.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1


Manager NEM Real Time Operations
     
127501INTER-REGIONAL TRANSFER11/06/2025 06:01:39 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_575BC182 from 1755 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1


Manager NEM Real Time Operations
     
127496INTER-REGIONAL TRANSFER11/06/2025 04:25:53 PM

Inter-regional transfer limit variation - Collector - Yass (3L) 330kV line - NSW region - 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector - Yass (3L) 330kV line - NSW region - 11/06/2025

A planned outage of Collector - Yass (3L) 330kV line in the NSW region was scheduled from 0700 hrs 10/06/2025 to 1500 hrs 16/06/2025.

The outage has been completed and Collector - Yass (3L) 330kV line returned to service at 1611 hrs 11/06/2025

Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE

Manager NEM Real Time Operations
     
127492INTER-REGIONAL TRANSFER10/06/2025 10:35:15 AM

Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE- QLD region - 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE - QLD region - 10/06/2025

At 1000 hrs 10/06/2025 there was a short notice outage of Middle Ridge - Greenbank (8848) 275 kV LINE.

The following constraint set(s) invoked at 1030 hrs 10/06/2025
Q-MRGB_8848_8849

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
127484MARKET SYSTEMS09/06/2025 01:25:11 AM

INC0145687 - RESOLVED - Frequency Performance Payments (FPP) System

INC0145687 - RESOLVED - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - RESOLVED

The service interruption relating to Frequency Performance Payments (FPP) System has been resolved.

The FPP System started normal operations from 00:25 Hrs AEST on 09/06/2025

Default Contribution Factors (DCFs) will be used for Regulation Frequency Control Ancillary Service (FCAS) recovery for the trading intervals where CFs were not calculated. No FPP amount will be paid or due for those Trading Intervals.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au

AEMO IT Duty Manager
     
127483MARKET SYSTEMS09/06/2025 12:02:59 AM

INC0145687 - ALERT - Frequency Performance Payments (FPP) Syste

INC0145687 - ALERT - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

AEMO is experiencing a service interruption relating to Frequency Performance Payments (FPP) System.

The service interruption started from 20:25 hrs AEST on 08/06/2025. The participants will experience a delay in receiving FPP factors.

AEMO is working on resolving the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au


































     
127474GENERAL NOTICE08/06/2025 12:12:12 AM

Network Augmentation Commissioned - NSW Region - 07/06/2025

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2350 hrs 07/06/2025 as follows:

Culcairn Solar Farm substation has been cut into the existing Walla Walla - Wagga 6Y 330 kV Transmission Line to form the following circuits:

Culcairn - Walla Walla 6Y 330 kV Transmission Line
Walla Walla - Wagga 3G 330 kV Transmission Line

Manager NEM Real Time Operations
     