127920MARKET INTERVENTION03/07/2025 06:19:48 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 04/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
127864RESERVE NOTICE25/06/2025 04:58:25 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127847 is cancelled at 1600 hrs on 25/06/2025.

No LOR3 condition is currently forecast in the STPASA period.

AEMO Operations
     
127847RESERVE NOTICE25/06/2025 02:48:13 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0630 hrs to 1100 hrs 02/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 108 MW at 0800 hrs.

2. From 1700 hrs 02/07/2025 to 0000 hrs 03/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 153 MW at 1900 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127844MARKET INTERVENTION25/06/2025 02:02:08 PM

Cancellation - AEMO Intervention Event - SA region 21/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 21/06/2025

Refer to Market Notice 127682

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 25/06/2025.


Manager NEM Real Time Operations
     
127843MARKET INTERVENTION25/06/2025 02:01:53 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127792

Direction is cancelled from: 1400 hrs 25/06/2025

Manager NEM Real Time Operations
     
127834GENERAL NOTICE25/06/2025 08:54:58 AM

Planned outage of Kiamal SF-Red Cliffs 220kV LINE in the VIC region on 27/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Kiamal SF-Red Cliffs 220kV LINE line in the Victorian (VIC) region is planned to be out of service from 0700 hrs on 27/06/2025 to 1630 hrs on 27/06/2025.

A credible contingency event during this planned outage may require:

* Load shedding in the Victorian outer grid; and/ or
* Market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
127792MARKET INTERVENTION24/06/2025 03:51:40 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127740

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 25/06/2025.

The direction update is issued at 1600 hrs 24/06/2025.

Manager NEM Real Time Operations
     
127773RESERVE NOTICE24/06/2025 09:45:42 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127753 is cancelled at 0900 hrs on 24/06/2025.

No LOR3 condition is currently forecast in the STPASA period.

AEMO Operations
     
127753RESERVE NOTICE23/06/2025 09:53:46 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period[s]:

[1.] From 0730 hrs 30/06/2025 to 0930 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 0800 hrs.

[2.] From 1700 hrs 30/06/2025 to 2300 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 112 MW at 1900 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     