Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 122297
Direction is cancelled from: 0400 hrs 21/12/2024
Manager NEM Real Time Operations
INC0139532 | Impact to Prudentials
SERVICE INTERRUPTION - ALERT
The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122279
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1445 hrs 20/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0400 hrs 21/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 22/12/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122277
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 22/12/2024.
The direction update is issued at 1445 hrs 20/12/2024.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for QLD from 20 Dec 2024 to 24 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Rockhampton Ap (39+ Deg C): 24th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 122283
The MINTARO MINTARO GAS direction is now expected to start at 0830 hrs 20/12/2024.
The direction update is issued at 0725 hrs 20/12/2024.
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 122276
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1700 hrs 19/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 20/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 21/12/2024.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
INC0139532 - ALERT - Impact to Prudentials
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to: Prudentials & Settlements.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Direction - {{REGION:SA}} region to {{UNIT.ParticipantName:Synergen Power Pty Limited}} - {{UNIT.DUIDName:MINTARO MINTARO GAS }}
Direction - {{REGION:SA}} region to {{UNIT.ParticipantName:Synergen Power Pty Limited}} - {{UNIT.DUIDName:MINTARO MINTARO GAS }}
Refer to Market Notice {{MNOTICE.NoticeID:122276}}
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to {{UNIT.ParticipantName:Synergen Power Pty Limited}}. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: {{UNIT.ParticipantName:Synergen Power Pty Limited}} - {{UNIT.DUIDName:MINTARO MINTARO GAS }} at {{Hrs[2]:1700}} hrs {{DATE:19/12/2024}}
Type of resource: {{RESOURCE_TYPE:generating unit}}
Required actions: {{DIRECTION_ACTION:Synchronise and follow dispatch targets}} at {{HRS[1]:0800}} hrs {{DATE[1]:20/12/2024}}
Services provided: {{SERVICES_PROVIDED:Voltage Control}}
Circumstances necessitating the Direction:{{DIRECTION_REASON:Voltage}}
Circumstances necessitating the Direction additional detail: {{DIRECTION_REASON_AD:intervention is required to maintain the power system in a secure operating state}}
Expected duration: {{Hrs[3]:0400}} hrs {{DATE[3]:21/12/2024}} / further notice.
{{UNIT.ParticipantName:Synergen Power Pty Limited}} does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations