Market Notices

119207MARKET SYSTEMS23/10/2024 10:25:05 AM

CHG0099235 | Production | Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.


Change Number: CHG0099235
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Change Start Date & Time: 24/10/2024 10:00:00 AEST
Change End Date & Time: 24/10/2024 16:00:00 AEST
Outage Start Date & Time: 24/10/2024 11:57:00 AEST
Outage End Date & Time: 24/10/2024 12:02:00 AEST
Environment: Production
Participant Impact and Requirements:
Planned maintenance has been scheduled for the 24th October, commencing 11:57am - 12:02pm AEST. During this time there will be a brief outage (Up to 30 seconds) impacting the following Pre-Production systems:

- MSATS Retail
- EMMS Wholesale
- GAS Market Systems
- WA Market Systems

The maintenance being carried out relates to infrastructure only, no application or functional changes are being performed. If you experience system related issues beyond the outage window (12:02pm) please contact the AEMO Support Hub.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .






     
119206MARKET SYSTEMS23/10/2024 10:21:46 AM

CHG0099241 | Production | Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.

Change Number: CHG0099241
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Change Start Date & Time: 24/10/2024 10:00:00 AEST
Change End Date & Time: 24/10/2024 16:00:00 AEST
Outage Start Date & Time: 24/10/2024 11:57:00 AEST
Outage End Date & Time: 24/10/2024 12:02:00 AEST
Environment: Production
Participant Impact and Requirements:
Planned maintenance has been scheduled for the 24th October, commencing 11:57am - 12:02pm AEST. During this time there will be a brief outage (Up to 30 seconds) impacting the following Pre-Production systems:

- MSATS Retail
- EMMS Wholesale
- GAS Market Systems
- WA Market Systems

The maintenance being carried out relates to infrastructure only, no application or functional changes are being performed. If you experience system related issues beyond the outage window (12:02pm) please contact the AEMO Support Hub.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .




     
119194MINIMUM SYSTEM LOAD22/10/2024 03:13:38 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 26/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 26/10/2024.

Minimum regional demand is forecast to be 1645 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1685 MW
MSL2 - 1185 MW
MSL3 - 685 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1230 hrs to 1300 hrs 26/10/2024.

AEMO Operations
     
119187MARKET SYSTEMS22/10/2024 01:31:16 PM

CHG0098837 | Completed | Pre-Production | EMMS-Pre-Production Bay transfer for Core switch Refresh

Change Number: CHG0098837

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Electricity Market Management System_PreProd

Change Title: EMMS-Pre-Production Bay transfer for Core switch Refresh

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
119183MARKET SYSTEMS22/10/2024 10:55:02 AM

CHG0098524 | Cancelled | Pre-Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production

Change Number: CHG0098524

Notification issued to: Market Notice

Notification Type: Cancelled

Change Type: Normal

Service/ Component: Short Term Trading Market (STTM)

Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
     
119139MARKET SYSTEMS21/10/2024 09:22:19 AM

CHG0098496 | Completed | Production | QLD Marketnet Router Replacement

Change Number: CHG0098496

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Market Network

Change Title: QLD Marketnet Router Replacement

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
119137MARKET SYSTEMS21/10/2024 08:20:38 AM

CHG0098837 | Pre-Production | EMMS-Pre-Production Bay transfer for Core switch Refresh

Change Number: CHG0098837

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Electricity Market Management System_PreProd

Change Title: EMMS-Pre-Production Bay transfer for Core switch Refresh

Change Start Date & Time: 22/10/2024 07:00:00 AEST
Change End Date & Time: 22/10/2024 19:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:

Environment: Pre-Production

Participant Impact and Requirements: A Bay transfer is scheduled for 22nd October is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
119029POWER SYSTEM EVENTS18/10/2024 03:48:56 PM

Non-credible contingency event - VIC region - 18/10/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 18/10/2024

At 1525 hrs the Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line tripped and auto-reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
119027GENERAL NOTICE18/10/2024 08:01:30 PM

Network Augmentation Commissioned - NSW Region - 18/10/2024

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2000 hrs 18/10/2024 as follows:

Stubo 330kV switching station has been cut into the existing Wellington - Wollar West 79 330 kV line to form the following circuits:

Wellington - Stubo SF 79 330 kV Transmission Line
Wollar West - Stubo SF 7M 330 kV Transmission Line

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm