Filter by category
Filter by Date
[EventId:202408051650_review] Prices for interval 05-Aug-2024 16:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 5 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Aug-2024 16:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408051645_review] Prices for interval 05-Aug-2024 16:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1640 hrs on 5 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Aug-2024 16:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408051640_review] Prices for interval 05-Aug-2024 16:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 5 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Aug-2024 16:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408051635_review] Prices for interval 05-Aug-2024 16:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 5 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Aug-2024 16:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024
Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024
A planned outage of Keilor to Sth Morang 500kV Line in the VIC region was scheduled from 1000 hrs 04/08/2024 to 1300 hrs 04/08/2024.
The outage has been completed and Keilor to Sth Morang 500kV Line returned to service at 1050 hrs 04/08/2024
Constraint set(s) revoked: V-KTSM_R
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the SA region - 30/07/2024
Cancellation of Actual (LOR1) condition in the SA region - 30/07/2024
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No. 117509 is cancelled at 2040 hrs 30/07/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 30/07/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 30/07/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2000 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs
The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 404 MW
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/07/2024
Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/07/2024
A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0830 hrs 26/07/2024 to 1730 hrs 28/07/2024.
The outage has been extended until 1200 hrs 29/07/2024
Constraint set(s) invoked:
I-HYSE
I-VS_050
I-VS+LKB_050
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 25/07/2024
Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 25/07/2024
A planned outage of Heywood M1 Transformer in the VIC region was scheduled from 0600 hrs 25/07/2024 to 1800 hrs 25/07/2024.
The outage has been completed and Heywood M1 Transformer returned to service at 1550 hrs 25/07/2024
Constraint set(s) revoked: V-HYTX_M12
Manager NEM Real Time Operations