[EventId:202406251340_review] Prices for interval 25-Jun-2024 13:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406251335_review] Prices for interval 25-Jun-2024 13:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406251330_review] Prices for interval 25-Jun-2024 13:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
CHG0090919 | Pre-Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market (STTM)
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Change Start Date & Time: 27/06/2024 08:00:00 AEST
Change End Date & Time: 27/06/2024 17:30:00 AEST
Outage Start Date & Time: 27/06/2024 09:00:00 AEST
Outage End Date & Time: 27/06/2024 13:30:00 AEST
Environment: Pre-Production
Participant Impact and Requirements:
This is a regular procedure to allow routine maintenance. Short service outages over the day for STTM services including SWEX and MIS.
Pre-Production Gas Short Term Trading Market (STTM)
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0090646 | Completed | Production | Planned maintenance affecting the AEMO Market Network.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Market Network
Change Title: Planned maintenance affecting the AEMO Market Network.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0090585 | Completed | Production | Dispatch Applications Upgrade
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: EMMS - Dispatch
Change Title: Dispatch Applications Upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0090725 | Pre-Production | Pre-Prod MSATS and eMDM July Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS and eMDM July Maintenance Release
Change Start Date & Time: 25/06/2024 13:00:00 AEST
Change End Date & Time: 25/06/2024 17:00:00 AEST
Outage Start Date & Time: 25/06/2024 13:00:00 AEST
Outage End Date & Time: 25/06/2024 17:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0090790 | Production | Maintenance activities to be performed on the Gas Full Retail Contestability (VIC/QLD) Market systems Production
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas FRC - CATS
Change Title: Maintenance activities to be performed on the Gas Full Retail Contestability (VIC/QLD) Market systems Production
Change Start Date & Time: 30/06/2024 09:00:00 AEST
Change End Date & Time: 30/06/2024 17:00:00 AEST
Outage Start Date & Time: 30/06/2024 10:00:00 AEST
Outage End Date & Time: 30/06/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the VIC & QLD RETAIL GFRC Production Systems will be unavailable.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Network Augmentation Commissioned - QLD Region - 21/06/2024
Network Augmentation Commissioned - QLD Region - 21/06/2024
Commissioned:
H90 Tully South - T48 Tully 7162 132kV line
H90 Tully South No.1 275kV /132 kV transformer
Manager NEM Real Time Operations