Market Notices

117337NON-CONFORMANCE12/07/2024 07:55:20 AM

NON-CONFORMANCE Region QLD1 Friday, 12 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 12 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 12/07/2024 07:05 to 12/07/2024 07:55
Amount: -74 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117321LOAD SHED08/07/2024 07:08:46 PM

Load Shedding Direction in the NSW Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the NSW Region

AEMO has directed load shedding commencing at 1817 hrs 08/07/2024
in the NSW region

to maintain power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
117312MARKET INTERVENTION07/07/2024 02:04:11 PM

Cancellation - AEMO Intervention Event - SA region 05/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 05/07/2024

Refer to Market Notice 117295

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 07/07/2024.



Manager NEM Real Time Operations
117311MARKET INTERVENTION07/07/2024 02:01:02 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 117310

Direction is cancelled from: 1400 hrs 07/07/2024

Manager NEM Real Time Operations
117310MARKET INTERVENTION07/07/2024 01:04:48 PM

Update - Direction - SA Region - 05/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 117303

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 07/07/2024.

The direction update is issued at 1300 hrs 07/07/2024.

Manager NEM Real Time Operations
117308NON-CONFORMANCE07/07/2024 09:30:22 AM

NON-CONFORMANCE Region QLD1 Sunday, 7 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 7 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TARONG#3
Duration: 07/07/2024 09:05 to 07/07/2024 09:30
Amount: -16 MW
Constraint: NC-Q_TARONG#3

Auto-generated on behalf of Manager NEM Real Time Operations
117305MARKET INTERVENTION06/07/2024 03:52:05 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 117293

Direction is cancelled from: 1600 hrs 06/07/2024

Manager NEM Real Time Operations
117304MARKET INTERVENTION06/07/2024 04:56:42 PM

Update - Direction - SA Region - 05/07/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 05/07/2024

Refer Market Notice 117295

The AEMO intervention event that commenced from interval ending 1705 hrs on 05/07/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
117303MARKET INTERVENTION06/07/2024 04:55:39 PM

Update - Direction - SA region 05/07/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA region 05/07/2024

Refer to Market Notice 117294


In accordance with section 116 of the National Electricity Law, AEMO is issuing an updated direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Updated - Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1700 hrs 06/07/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0400 hrs 07/07/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 07/07/2024

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm