Market Notices

117451RECLASSIFY CONTINGENCY25/07/2024 06:56:46 PM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 25/07/2024 18:56 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
117450RECLASSIFY CONTINGENCY25/07/2024 06:56:45 PM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 25/07/2024 18:56 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
117412MARKET SYSTEMS22/07/2024 09:52:44 AM

CHG0090458 | Completed | Production | Planned Maintenance to Brisbane Internet firewall.

Change Number: CHG0090458
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet firewall.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117403MARKET SYSTEMS21/07/2024 02:12:21 PM

CHG0091275 | Completed | Production | MSATS - eMDM Maintenance AKS v1.28 upgrade

Change Number: CHG0091275
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS - eMDM Maintenance AKS v1.28 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117402RECLASSIFY CONTINGENCY21/07/2024 01:54:16 PM

Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Cancellation time: 21/07/2024 13:54

Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Refer AEMO Electricity Market Notice 117401

Auto-generated on behalf of Manager NEM Real Time Operations
117401RECLASSIFY CONTINGENCY21/07/2024 12:51:46 PM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Duration: 21/07/2024 12:51 until further notice

Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Auto-generated on behalf of Manager NEM Real Time Operations
117392RECLASSIFY CONTINGENCY20/07/2024 04:12:34 PM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - South Australia and Victoria regions.

AEMO ELECTRICITY MARKET NOTICE.

AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 117373 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 1610 hrs 20/07/2024.

Constraint set(s) revoked:
I-SV_250
I-VS_250

Manager NEM Real Time Operations
117391RECLASSIFY CONTINGENCY20/07/2024 04:08:54 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Cancellation time: 1600 hrs 20/07/2024
Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 117358.

Manager NEM Real Time Operations
117390RECLASSIFY CONTINGENCY20/07/2024 04:07:20 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Cancellation time: 1600 hrs 20/07/2024
Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 117363.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm