117061MARKET INTERVENTION18/06/2024 11:25:29 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 20/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
117058MARKET SYSTEMS18/06/2024 06:04:46 PM

CHG0090782 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Number: CHG0090782

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Start Date & Time: 26/06/2024 09:00:00 AEST
Change End Date & Time: 26/06/2024 22:00:00 AEST
Outage Start Date & Time: 26/06/2024 18:30:00 AEST
Outage End Date & Time: 26/06/2024 21:00:00 AEST

Environment: Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
117047MARKET SYSTEMS18/06/2024 01:48:46 PM

CHG0090106 | Cancelled | Production | Identity Service Site Transfer

Change Number: CHG0090106

Notification issued to: Market Notice
Notification Type: Cancelled

Change Type: Normal
Service/ Component: Identity Service (IDS)

Change Title: Identity Service Site Transfer

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117044MARKET SYSTEMS18/06/2024 11:44:51 AM

CHG0089794 | Cancelled | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities

Change Number: CHG0089794

Notification issued to: Market Notice
Notification Type: Cancelled

Change Type: Normal
Service/ Component: Electricity Market Management System

Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117037MARKET SYSTEMS18/06/2024 08:21:17 AM

CHG0090550 | Cancelled | Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Change Number: CHG0090550
Notification issued to: Market Notice

Notification Type: Cancelled
Change Type: Normal
Service/ Component: Gas FRC - CATS

Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117029MARKET SYSTEMS17/06/2024 01:55:46 PM

CHG0089836 | Completed | Pre-Production | Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.

Change Number: CHG0089836
Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal
Service/Component: Gas Hub

Change Title: Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117021RESERVE NOTICE15/06/2024 08:03:58 PM

Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117020 is cancelled at 1900 hrs 15/06/2024.

Manager NEM Real Time Operations
117020RESERVE NOTICE15/06/2024 05:14:10 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/06/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1780 MW
The minimum capacity reserve available is 1446 MW

Manager NEM Real Time Operations
117014MARKET INTERVENTION14/06/2024 08:29:53 PM

Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024

Refer Market Notice 116996

AEMO no longer foresees a possible requirement for intervention to manage power system security in QLD region. The advice of possible intervention is cancelled from 2030 hrs 14/06/2024.

Manager NEM Real Time Operations