Market Notices

116922NON-CONFORMANCE10/06/2024 08:30:13 AM

NON-CONFORMANCE Region SA1 Monday, 10 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 10 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CATHROCK
Duration: 10/06/2024 08:10 to 10/06/2024 08:30
Amount: 22 MW
Constraint: NC-S_CATHROCK

Auto-generated on behalf of Manager NEM Real Time Operations
116913NON-CONFORMANCE09/06/2024 08:55:15 AM

NON-CONFORMANCE Region NSW1 Sunday, 9 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 9 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 09/06/2024 08:50 to 09/06/2024 08:55
Amount: 34 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
116910RESERVE NOTICE07/06/2024 03:46:01 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 13/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 116905 is cancelled at 1400 hrs 07/06/2024.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
116908NON-CONFORMANCE07/06/2024 12:00:22 PM

NON-CONFORMANCE Region VIC1 Friday, 7 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 7 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS3
Duration: 07/06/2024 11:55 to 07/06/2024 12:00
Amount: -84 MW
Constraint: NC-V_YWPS3

Auto-generated on behalf of Manager NEM Real Time Operations
116905RESERVE NOTICE06/06/2024 02:54:08 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 13/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1730 hrs to 2100 hrs 13/06/2024.
The forecast capacity reserve requirement is 439 MW.
The minimum capacity reserve available is 382 MW.


AEMO Operations

116899GENERAL NOTICE05/06/2024 12:11:55 PM

Network Augmentation Commissioned - QLD Region - 05/06/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 05/06/2024

H20 Broadsound 275 kV Bus Reactor 1 (150 MVAr) has been commissioned as at 1043 hrs.

Manager NEM Real Time Operations
116883NON-CONFORMANCE04/06/2024 06:00:20 AM

NON-CONFORMANCE Region VIC1 Tuesday, 4 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 4 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MACARTH1
Duration: 04/06/2024 05:55 to 04/06/2024 06:00
Amount: 34 MW
Constraint: NC-V_MACARTH1

Auto-generated on behalf of Manager NEM Real Time Operations
116882RESERVE NOTICE03/06/2024 05:49:43 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 04/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 116881 for the 04/06/2024 is cancelled at 1745 hrs 03/06/2024.

Manager NEM Real Time Operations
116881RESERVE NOTICE03/06/2024 05:20:08 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 04/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1700 hrs 04/06/2024 to 1730 hrs 04/06/2024.
The forecast capacity reserve requirement is 448 MW.
The minimum capacity reserve available is 411 MW.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm