Network Augmentation Commissioned - NSW Region - 10/09/2024
Network Augmentation Commissioned - NSW Region - 10/09/2024
At 1750 hrs, the following equipment at Buronga 330 kV substation has been commissioned:
1) Buronga 330 kV A bus.
2) Buronga 330 kV B bus.
3) Buronga No 1 330 kV capacitor.
4) Buronga No 2 330 kV capacitor.
5) Buronga No 7 330/220 kV transformer.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118202 is cancelled at 1100 hrs 09/09/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1830 hrs to 1930 hrs 10/09/2024.
The forecast capacity reserve requirement is 347 MW.
The minimum capacity reserve available is 343 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118200 is cancelled at 0030 hrs 09/09/2024.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 1830 hrs 10/09/2024 to 2030 hrs 10/09/2024.
The forecast capacity reserve requirement is 430 MW.
The minimum capacity reserve available is 403 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202409081835_review] Prices for interval 08-Sep-2024 18:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409081830_review] Prices for interval 08-Sep-2024 18:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409081825_review] Prices for interval 08-Sep-2024 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409081820_review] Prices for interval 08-Sep-2024 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.