Network Augmentation Commissioned - NSW Region - 18/10/2024
A network augmentation has been commissioned in the NSW region at 2000 hrs 18/10/2024 as follows:
Stubo 330kV switching station has been cut into the existing Wellington - Wollar West 79 330 kV line to form the following circuits:
Wellington - Stubo SF 79 330 kV Transmission Line
Wollar West - Stubo SF 7M 330 kV Transmission Line
Manager NEM Real Time Operations
[EventId:202410172040_confirmed] Prices for interval 17-Oct-2024 20:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2100 hrs on 17 October 2024
PRICES ARE NOW CONFIRMED for trading interval 17-Oct-2024 20:40.
In accordance with Market Notice 119002 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410172100_confirmed] Prices for interval 17-Oct-2024 21:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2100 hrs on 17 October 2024
PRICES ARE NOW CONFIRMED for trading interval 17-Oct-2024 21:00.
In accordance with Market Notice 119006 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410172055_confirmed] Prices for interval 17-Oct-2024 20:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2100 hrs on 17 October 2024
PRICES ARE NOW CONFIRMED for trading interval 17-Oct-2024 20:55.
In accordance with Market Notice 119005 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410172050_confirmed] Prices for interval 17-Oct-2024 20:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2100 hrs on 17 October 2024
PRICES ARE NOW CONFIRMED for trading interval 17-Oct-2024 20:50.
In accordance with Market Notice 119004 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410172045_confirmed] Prices for interval 17-Oct-2024 20:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2100 hrs on 17 October 2024
PRICES ARE NOW CONFIRMED for trading interval 17-Oct-2024 20:45.
In accordance with Market Notice 119003 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410172035_confirmed] Prices for interval 17-Oct-2024 20:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2100 hrs on 17 October 2024
PRICES ARE NOW CONFIRMED for trading interval 17-Oct-2024 20:35.
In accordance with Market Notice 119001 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the QLD region - 17/10/2024
Cancellation of Actual (LOR1) condition in the QLD region - 17/10/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.118993 is cancelled at 1839 hrs 17/10/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 17/10/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 17/10/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1136 MW
The minimum capacity reserve available is 1076 MW
Manager NEM Real Time Operations