Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Cancellation time: 1600 hrs 20/07/2024
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 117363.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 20 July 2024
NON-CONFORMANCE QLD1 Region Saturday, 20 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANGARR1
Duration: 20/07/2024 12:20 to 20/07/2024 13:50
Amount: 60 MW
Constraint: NC-Q_GANGARR1
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - South Australia and Victoria regions.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely widespread severe weather in the South Australia and Victoria regions.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.
AEMO has taken the following action(s) to maintain power system security at 1740 hrs 19/07/2024.
Constraint set(s) invoked:
I-SV_250
I-VS_250
Duration: until further notice
Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.
Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Duration: 18/07/2024 17:30 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.
Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Duration: 18/07/2024 11:30 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 14 July 2024
NON-CONFORMANCE QLD1 Region Sunday, 14 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 14/07/2024 16:35 to 14/07/2024 16:50
Amount: -66 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Sunday, 14 July 2024
NON-CONFORMANCE VIC1 Region Sunday, 14 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS1
Duration: 14/07/2024 01:40 to 14/07/2024 01:45
Amount: -35 MW
Constraint: NC-V_YWPS1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Cancellation time: 13/07/2024 16:44
Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Refer AEMO Electricity Market Notice 117340
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Duration: 13/07/2024 15:41 until further notice
Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Auto-generated on behalf of Manager NEM Real Time Operations