Market Notices

117340RECLASSIFY CONTINGENCY13/07/2024 03:41:56 PM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 13/07/2024 15:41 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
117337NON-CONFORMANCE12/07/2024 07:55:20 AM

NON-CONFORMANCE Region QLD1 Friday, 12 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 12 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 12/07/2024 07:05 to 12/07/2024 07:55
Amount: -74 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117308NON-CONFORMANCE07/07/2024 09:30:22 AM

NON-CONFORMANCE Region QLD1 Sunday, 7 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 7 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TARONG#3
Duration: 07/07/2024 09:05 to 07/07/2024 09:30
Amount: -16 MW
Constraint: NC-Q_TARONG#3

Auto-generated on behalf of Manager NEM Real Time Operations
117307RECLASSIFY CONTINGENCY06/07/2024 11:04:37 PM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.

AEMO ELECTRICITY MARKET NOTICE.

AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 117306 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 2300 hrs 06/07/2024.

Constraint set revoked: I-VS_250

Manager NEM Real Time Operations
117306RECLASSIFY CONTINGENCY06/07/2024 09:34:08 PM

Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.

AEMO ELECTRICITY MARKET NOTICE.

AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely severe weather in the SA region.

AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

AEMO has taken the following action to maintain power system security at 2120 hrs 06/07/2024.

Constraint set invoked: I-VS_250

Duration: 2120 hrs 06/07/2024 until further notice

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).

Manager NEM Real Time Operations
117302NON-CONFORMANCE06/07/2024 01:55:24 PM

NON-CONFORMANCE Region SA1 Saturday, 6 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Saturday, 6 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BOWWPV1
Duration: 06/07/2024 13:20 to 06/07/2024 13:55
Amount: 6 MW
Constraint: NC-S_BOWWPV1

Auto-generated on behalf of Manager NEM Real Time Operations
117299NON-CONFORMANCE06/07/2024 04:30:14 AM

NON-CONFORMANCE Region QLD1 Saturday, 6 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 6 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 06/07/2024 04:00 to 06/07/2024 04:30
Amount: 33 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117298RECLASSIFY CONTINGENCY06/07/2024 02:40:53 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Cancellation time: 1400 hrs 06/07/2024
Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 117297

Manager NEM Real Time Operations
117297RECLASSIFY CONTINGENCY05/07/2024 09:29:06 PM

Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Duration: 05/07/2024 21:30 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm