Cancellation - MSL1- VIC Region at 0500 hrs 13/10/2024.
Cancellation - MSL1- VIC Region at 0500 hrs 13/10/2024.
Refer to Market Notice 118809 for MSL1.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118810
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 13/10/2024.
The direction update is issued at 2130 hrs 12/10/2024.
Manager NEM Real Time Operations
Cancellation - MSL1- VIC Region at 1247 hrs 12/10/2024.
Cancellation - MSL1- VIC Region at 1247 hrs 12/10/2024.
Refer to Market Notice 118803 for MSL1.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118772
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 13/10/2024.
The direction update is issued at 1400 hrs 12/10/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118773
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 13/10/2024.
The direction update is issued at 1400 hrs 12/10/2024.
Manager NEM Real Time Operations
Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024
Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024
Update to Market Notice 118749 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1200 hrs 13/10/2024 to 1230 hrs 13/10/2024.
Minimum regional demand is [forecast to be] 1557 MW at 1230 hrs, and the advisory threshold is:
? MSL1 - 1560 MW
? MSL2 - 1010 MW
? MSL3 - 510 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the xxx threshold. Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response such as rescheduling of planned network outages and increasing electricity consumption.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
Manager NEM Real Time Operations
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 12/10/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1230 hrs 12/10/2024 to 1330 hrs 12/10/2024.
Minimum regional demand is forecast to be 1585 MW at 1300 hrs, and the advisory threshold is:
o MSL1 - 1605 MW
o MSL2 - 1105 MW
o MSL3 - 605 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
AEMO Operations
Cancellation - Forecast Minimum System Load 1 (MSL1) in the VIC Region on 12/10/2024
Cancellation - MSL1 - VIC Region at 1400 hrs 11/10/2024.
Refer to Market Notice 118646 for MSL1.
AEMO Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 118767
Direction is cancelled from: 1800 hrs 11/10/2024